Show on map
Oconto Falls Upper — Power plant · Hydro · Eagle Creek Renewable Energy, LLC
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Oconto Falls Upper

Power plant · Hydro

Key facts

Power plant · Hydroran 62% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1918
Net generation, 2025
5,995 MWh
Grid
34 kV to Wisconsin Electric Power Co (MISO)
Location
Oconto County, Wisconsin

Output

Net generation MWh by year, 2003 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
108 years since 1918
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
MRO
Report year
2025
Grid voltage kv
34.50
Transmission owner
Wisconsin Electric Power Co
Balancing authority code
MISO
Balancing authority name
Midcontinent Independent Transmission System Operator, Inc..
Fuel burned (MMBtu), 202520,455
Capacity factor, 20250.622
Net generation (MWh), 20255,995
Balancing authority codeMISO

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Eagle Creek Renewable Energy, LLC Operator EIA-860M
N.E.W. Hydro, LLC Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M