- Combustion
- Wind & solar
- In development
- Retired
- 10 · 100 · 1,000 MW
Map
- Combustion
- Wind & solar
- In development
- Retired
Paulding: location and 1 exact-grade project within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Paulding
Power plant · Oil
Key facts
Power plant · Oil Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1972
- Net generation, 2018
- 0 MWh
- Grid
- 69 kV to South Mississippi El Pwr Assn (MISO)
- Location
- Jasper County, Mississippi
- Operated by
- Cooperative EnergySourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Oil
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Oil source: “Petroleum Liquids”
- Age
- 54 years since 1972
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | MISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- August 2017
- Capacity retired
- 20 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| 1 | Petroleum Liquids | 20 MW | Retired | August 2017 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 69 kV
- Transmission or distribution system owner
- South Mississippi El Pwr Assn
- Balancing authority
- Midcontinent Independent Transmission System Operator, Inc..
- NERC region
- SERC
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit 1 scheduled to retire, 20 MW · EIA-860M
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| SR Jasper Permitted | Solar | 13.5 km | 150 |