Show on map
Paulding — Power plant · Oil · Cooperative Energy
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oil Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1972
Net generation, 2018
0 MWh
Grid
69 kV to South Mississippi El Pwr Assn (MISO)
Location
Jasper County, Mississippi
Operated by
Cooperative EnergySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2018
0MWh
Fuel burned, 2018
0MMBtu
Capacity factor, 2018
Not stated
Heat rate, 2018
Not stated
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
201800——
20173416,2250.2%18,255
2016401,1460.0%28,650
2015-1742——
2014154790.0%—
20131513,0860.1%20,437
201291130.0%12,556
2011217870.0%—
2010284460.0%15,929
2009193810.0%20,053
2008425850.0%13,929
2007335860.0%17,757
2006501,1850.0%23,700
200500——
2004447480.0%17,000
2003501,1720.0%23,440
20021041,6960.1%16,308
2001831,5070.1%18,157
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

Every source and license · Attribution

View at source