Show on map
- Clean firm
- Wind & solar
- Storage
- In development
- Under construction
- Operating
- 10 · 100 · 1,000 MW
Map
- Clean firm
- Wind & solar
- Storage
- In development
- Under construction
- Operating
Pome BESS: location and 9 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Pome BESS
Power plant · Storage
Key facts
Power plant · Storage Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2025
- Grid
- 138 kV to San Diego Gas & Electric Co (CISO)
- Location
- San Diego County, California
- Operated by
- MN8 Energy LLC
Output
Details
Who’s behind it
- Owner
- Pome BESS LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Storage source: “Batteries”
- Age
- 1 year since 2025
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 0 |
| Net generation (MWh), 2025 | -7,903 |
| Balancing authority code | CISO |
Data notes (1)
- Capacity factor, 2025 not shown: net generation -7903.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| MN8 Energy LLC | Operator | EIA-860M | ||
| Pome BESS LLC | Owner | 100.0% | Dec 31, 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Pomerado Energy Storage, LLC Postponed | Storage | 0.5 mi | 6 |
| Rancho Penasquitos Under construction | Hydro | 4.7 mi | 4.3 |
| L3 Harris San Diego Under construction | Solar | 10.1 mi | 1.6 |
| EnerSmart Murray BESS Postponed | Storage | 10.4 mi | 21 |
| EnerSmart Mesa Heights Sub Station Under construction | Storage | 10.6 mi | 3 |
| Alvarado Hydro Facility Postponed | Hydro | 11.0 mi | 1.4 |
| EnerSmart El Cajon BESS Postponed | Storage | 11.2 mi | 3 |
| Enterprise BESS Permitted | Storage | 13.5 mi | 54.1 |
| Don Lee BESS 1 LLC Postponed | Storage | 14.0 mi | 6.5 |
Sources EIA-860M