Show on map
Red Cloud — Power plant · Oil · City of Red Cloud - (NE)
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1953
Net generation, 2025
37 MWh
Grid
14 kV to City of Red Cloud - (NE) (SWPP)
Location
Webster County, Nebraska
Operated by
City of Red Cloud - (NE)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
73 years since 1953
Unused energy
50 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
10,216 Btu/kWh 2025
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 2025378
Capacity factor, 20250.001
Heat rate (Btu/kWh), 202510,216.2
Net generation (MWh), 202537
Balancing authority codeSWPP

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
0.5 MW
Generators retired
1
Capacity still in service
5.7 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Petroleum Liquids0.5 MWRetiredFebruary 2002

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
14 kV
Transmission or distribution system owner
City of Red Cloud - (NE)
Balancing authority
Southwest Power Pool
NERC region
MRO
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 1 scheduled to retire, 0.5 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

View at source