Show on map
Red Hawk — Power plant · Gas, combined cycle · Arizona Public Service Co
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Gas, combined cycle

Key facts

Power plant · Gas, combined cycleran 49% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2002
Net generation, 2025
4,842,624 MWh
Grid
500 kV to Salt River Project (SRP)
Location
Maricopa County, Arizona

Operations

Net generation, 2025
4,842,624MWh
Fuel burned, 2025
34,261,781MMBtu
Capacity factor, 2025
49.0%
Heat rate, 2025
7,075Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
2026 (8 of 12 months)3,663,64226,270,855—7,171
20254,842,62434,261,78149.0%7,075
20244,173,91529,631,86642.2%7,099
20234,430,50931,186,57944.9%7,039
20225,014,33335,721,52650.8%7,124
20215,489,82338,718,51955.6%7,053
20205,568,84839,232,96256.2%7,045
20194,650,22634,914,00947.1%7,508
2018 (11 of 12 months)3,591,88626,821,464—7,467
20174,396,30632,990,73444.5%7,504
20165,158,89938,428,22752.1%7,449
20154,525,26933,793,39545.8%7,468
20143,684,78728,091,55137.3%7,624
20133,773,39628,102,13238.2%7,447
20124,673,74034,395,99947.2%7,359
20113,575,55226,695,32136.2%7,466
20103,376,01225,558,65234.2%7,571
20094,006,35830,260,81240.6%7,553
20084,151,07131,343,37841.9%7,551
20074,201,84531,552,51542.6%7,509
20064,915,67536,516,93749.8%7,429
20053,849,12428,549,33439.0%7,417
20042,330,37617,197,53723.5%7,380
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

3 sources

Sources EIA-860M · GEM · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution

View at source