Show on map
Smith Street — Power plant · Oil · New Smyrna Beach Utilities Commission
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Smith Street

Power plant · Oil

Key facts

Power plant · Oil Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1946
Net generation, 2013
0 MWh
Grid
23 kV (NSB)
Location
Volusia County, Florida
Operated by
New Smyrna Beach Utilities CommissionSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2013
Fuel burned MMBtu by year, 2001 to 2013
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
80 years since 1946
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeNSB

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2013
Capacity retired
12.5 MW
Generators retired
8
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
10Petroleum Liquids2 MWRetiredDecember 2013
11Petroleum Liquids2 MWRetiredDecember 2013
3Petroleum Liquids0.8 MWRetiredDecember 2013
4Petroleum Liquids1 MWRetiredDecember 2013
6Petroleum Liquids1.8 MWRetiredDecember 2013
7Petroleum Liquids1.8 MWRetiredDecember 2013
8Petroleum Liquids1.1 MWRetiredDecember 2013
9Petroleum Liquids2 MWRetiredDecember 2013

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
23 kV
Balancing authority
New Smyrna Beach, Utilities Commission of
NERC region
SERC
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 10, 11, 3, 4, 6, 7, 8, 9 scheduled to retire, 12.5 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 9, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source