Show on map
TalenEnergy Susquehanna — Power plant · Nuclear · TalenEnergy Susquehanna LLCCUMULUS DATA CENTER — Under construction · Large load · PA · 0.2 mi awaySalem Route 11 Solar LLC — Permitted · Solar · PA · 3 MW · 3.1 mi awayData Center — Filed · Large load · PA · 10.1 mi awayPF Onsite BESS — Filed · Storage · PA · 21 MW · 12.5 mi awayCottontail Solar 7 — Postponed · Solar · PA · 21.1 MW · 14.3 mi away
  • Clean firm
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

TalenEnergy Susquehanna

Power plant · Nuclear

Key facts

Power plant · Nuclearran 84% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1983
Net generation, 2025
18,566,666 MWh
Grid
500 kV, 230 kV to PPL Electric Utilities Corp (PJM)
Location
Luzerne County, Pennsylvania

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Nuclear

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Nuclear source: “Nuclear”
Age
43 years since 1983
Heat rate
10,443 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
500, 230
Transmission owner
PPL Electric Utilities Corp
Balancing authority code
PJM
Balancing authority name
PJM Interconnection, LLC
Fuel burned (MMBtu), 2025193,898,872
Capacity factor, 20250.837
Heat rate (Btu/kWh), 202510,443.4
Net generation (MWh), 202518,566,666
Balancing authority codePJM

Ownership

2 companies3
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
TalenEnergy Susquehanna LLC Operator EIA-860M
Allegheny Electric Coop Inc Owner 10.0% Dec 31, 2025 EIA-860
TalenEnergy Susquehanna LLC Owner 90.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
CUMULUS DATA CENTER Under construction Large load 0.2 mi
Salem Route 11 Solar LLC Permitted Solar 3.1 mi 3
Data Center Filed Large load 10.1 mi
PF Onsite BESS Filed Storage 12.5 mi 21
Cottontail Solar 7 Postponed Solar 14.3 mi 21.1

Sources EPA ICIS-NPDES · EIA-860M · FAA OE/AAA

Sources

Attribution