Show on map
- Wind & solar
- Storage
- In development
- Under construction
- Operating
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Storage
- In development
- Under construction
- Operating
Tynan: location and 3 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Tynan
Power plant · Storage
Key facts
Power plant · Storage Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2025
- Net generation, 2025
- -130 MWh
- Grid
- 12 kV to AEP Texas Central Company (ERCO)
- Location
- Bee County, Texas
- Operated by
- HEN Infrastructure, L.L.C.
Output
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Storage source: “Batteries”
- Age
- 1 year since 2025
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 0 |
| Net generation (MWh), 2025 | -130 |
| Balancing authority code | ERCO |
Data notes (1)
- Capacity factor, 2025 not shown: net generation -130.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
Ownership
4 companies4| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| HEN Infrastructure, L.L.C. | Operator | EIA-860M | ||
| John Hancock Funding Company | Owner | 43.4% | 31 Dec 2025 | EIA-860 |
| Manulife Infrastructure II Holdings A, L.P. | Owner | 53.2% | 31 Dec 2025 | EIA-860 |
| Hunt Energy Network, LLC | Owner | 3.4% | 31 Dec 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Honeycomb Solar and Storage Under construction | Solar + storage | 0.1 km | 137.9 |
| Bird Dog Energy Storage Built | Storage | 9.2 km | 60.4 |
| Abeja Solar Farm Contracted | Solar | 13.3 km | 200.8 |