Show on map
Tyson Nick — Power plant · Solar · Tyson Nick Solar Project, LLCMRG Goody Solar Project Hybrid — Solar + storage · TX · 223.1 MW · 0.7 km awayRoscommon Solar Park — Solar · TX · 82.8 MW · 6.5 km awayPARIS DATA CENTER PROJECT — Large load · TX · 8.9 km awayRowdy Creek Solar and BESS — Solar + storage · TX · 701.8 MW · 12.6 km awayEchols Grove Solar — Solar · TX · 200.9 MW · 15.9 km awayEagle Springs Hybrid — Solar + storage · TX · 111.2 MW · 24.0 km away
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Solar

Key facts

Power plant · Solar Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2025
Grid
138 kV to Oncor Electric Delivery Company LLC (ERCO)
Location
Lamar County, Texas

Output

Net generation MWh by year, 2025 to 2026

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Solar source: “Solar Photovoltaic”
Age
1 year since 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001058787
Location id
L100001051016
Eia plant ids
68856
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
138
Transmission owner
Oncor Electric Delivery Company LLC
Balancing authority code
ERCO
Balancing authority name
Electric Reliability Council of Texas, Inc.
Fuel burned (MMBtu), 2025129,417
Capacity factor, 20250.048
Net generation (MWh), 202537,930
Balancing authority codeERCO

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Tyson Nick Solar Project, LLC Operator EIA-860M
CVI Renewables Holdings, LLC. Owner 100.0% 31 Dec 2025 EIA-860

Timeline

  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
MRG Goody Solar Project Hybrid Built Solar + storage 0.7 km 223.1
Roscommon Solar Park Permitted Solar 6.5 km 82.8
PARIS DATA CENTER PROJECT Built Large load 8.9 km
Rowdy Creek Solar and BESS Under construction Solar + storage 12.6 km 701.8
Echols Grove Solar Contracted Solar 15.9 km 200.9
Eagle Springs Hybrid Under construction Solar + storage 24.0 km 111.2