Show on map
- Combustion
- Wind & solar
- Storage
- Loads
- In development
- Under construction
- Operating
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Combustion
- Wind & solar
- Storage
- Loads
- In development
- Under construction
- Operating
- Size not stated
WAL3432: location and 20 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
WAL3432
Power plant · Gas, reciprocating engine
Key facts
Power plant · Gas, reciprocating engineran 3% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2021
- Net generation, 2025
- 279 MWh
- Grid
- 0.5 kV to Oncor Electric Delivery Company LLC (ERCO)
- Location
- Dallas County, Texas
- Operated by
- Walmart Stores Texas, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
- Age
- 5 years since 2021
- Unused energy
- 10 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 9,986 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 2,786 |
| Capacity factor, 2025 | 0.026 |
| Heat rate (Btu/kWh), 2025 | 9,985.7 |
| Net generation (MWh), 2025 | 279 |
| Balancing authority code | ERCO |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Emerald Hill Energy Storage Postponed | Storage | 1.5 km | 250 |
| Cedar Hill ESS Filed | Storage | 4.7 km | 10 |
| ALAMO MISSION Built | Large load | 10.1 km | |
| CC6800 - Mustang RED2 (Red Oak data centre) Filed | Large load | 10.5 km | |
| MEI Temporary Crane (Lancaster data centre) Filed | Large load | 11.0 km | |
| LANCASTER DATA CENTER Under construction | Large load | 11.1 km | |
| TX Dallas 7750 Dynasty Drive Under construction | Solar | 13.4 km | 2.3 |
| QTS - DFW 3 - DC1 Filed | Large load | 13.6 km | |
| STACK DFW02A (Lancaster data centre) Under construction | Large load | 13.8 km | |
| Databank Red Oak Campus - DFW 11 Filed | Large load | 15.1 km | |
| Databank 13 Filed | Large load | 15.9 km | |
| Stream Fir Data Center Filed | Large load | 16.7 km | |
| WAL4279 Postponed | Gas, reciprocating engine | 16.8 km | 1.2 |
| QTS Data Centers 6 and 7 Filed | Large load | 17.2 km | |
| Dolomite Storage Filed | Storage | 20.2 km | 125.7 |
| AREP Powerhouse Crane (Midlothian data centre) Filed | Large load | 21.5 km | |
| SHARKA Built | Large load | 23.2 km | |
| EQUINIX N STEMMONS FREEWAY DALLAS Built | Large load | 23.7 km | |
| EXXONMOBIL DALLAS DATA CENTER Built | Large load | 24.1 km | |
| TX 14 Venus Mill Storage Postponed | Storage | 24.7 km | 100 |
Sources EIA-860M · EPA ICIS-Air · FAA OE/AAA · EPA ICIS-NPDES · ERCOT
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA ECHO ICIS-Air national facility download (data-centre selection, placed through FRS)
- FAA OE/AAA Part 77 obstruction evaluation case archives (data-centre sites, buildings and cranes)
- EPA ECHO ICIS-NPDES construction stormwater coverage (data-centre sites, national)
- ERCOT GIS Report (Generator Interconnection Status)