Wheaton
Power plant · Gas, combustion turbine
Key facts
Power plant · Gas, combustion turbineran 1% of 2024 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2025
- Net generation, 2024
- 18,592 MWh
- Grid
- 161 kV to Northern States Power Co (MISO)
- Location
- Chippewa County, Wisconsin
- Operated by
- Northern States Power Co - Minnesota
Output
- Gas
- Oil
Details
Who’s behind it
- Owner
- Xcel Energy
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Age
- 1 year since 2025
- Unused energy
- 2,603 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 16,785 Btu/kWh 2025
All 7 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 140,539 |
| Capacity factor, 2025 | 0.003 |
| Heat rate (Btu/kWh), 2025 | 16,784.8 |
| Net generation (MWh), 2025 | 8,373 |
| Balancing authority code | MISO |
Retirement
EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.- Capacity retired
- 300.2 MW
- Generators retired
- 6
- Capacity still in service
- 298.1 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| 5 | Petroleum Liquids | 53.1 MW | Retired | June 2018 |
| 6 | Petroleum Liquids | 53.1 MW | Retired | January 2024 |
| 1 | Natural Gas Fired Combustion Turbine | 48.5 MW | Retired | May 2025 |
| 2 | Natural Gas Fired Combustion Turbine | 48.5 MW | Retired | May 2025 |
| 3 | Natural Gas Fired Combustion Turbine | 48.5 MW | Retired | May 2025 |
| 4 | Natural Gas Fired Combustion Turbine | 48.5 MW | Retired | May 2025 |
By technology
| Technology | Retired | Scheduled to retire |
|---|---|---|
| Natural Gas Fired Combustion Turbine | 194 MW | |
| Petroleum Liquids | 106.2 MW |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 161 kV
- Transmission or distribution system owner
- Northern States Power Co
- Balancing authority
- Midcontinent Independent Transmission System Operator, Inc..
- NERC region
- MRO
Transmission lines within 25 km (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Northern States Power Co - Minnesota | Operator | EIA-860M | ||
| Xcel Energy | Owner | 100.0% | 31 Dec 2023 | EPA GHGRP |
Timeline
- Stated Units 1, 2, 3, 4 scheduled to retire, 194 MW · EIA-860M
- In service · EIA-860M
- Stated Unit 6 scheduled to retire, 53.1 MW · EIA-860M
- Stated Unit 5 scheduled to retire, 53.1 MW · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Elk Mound Postponed | Gas, combustion turbine | 4.5 km | 71 |
| Seven Mile Creek LFG Postponed | Biomass | 12.8 km | 0.8 |