Yazoo — Power plant · Gas, combined cycle · Public Serv Comm of Yazoo City -(MS)
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Gas, combined cycle

Key facts

Power plant · Gas, combined cycle Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1945
Net generation, 2024
0 MWh
Grid
115 kV to Public Serv Comm of Yazoo City (MISO)
Location
Yazoo County, Mississippi
Operated by
Public Serv Comm of Yazoo City -(MS)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2024
Fuel burned MMBtu by year, 2002 to 2024
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
Age
81 years since 1945
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2021
Capacity retired
34.1 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
2Natural Gas Fired Combined Cycle5 MWRetiredDecember 2021
3Natural Gas Fired Combined Cycle12.6 MWRetiredDecember 2021
GT1Natural Gas Fired Combined Cycle16.5 MWRetiredDecember 2021

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV
Transmission or distribution system owner
Public Serv Comm of Yazoo City
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
SERC
Transmission lines within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 2, 3, GT1 scheduled to retire, 34.1 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source