Key facts
Solar + storage Built (source status: Operating (EIA-860M operating generator inventory)) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Queue position
- 1314
- In-service date
- (stated)
- Location
- SAN BERNARDINO County, California (exact site not public)
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Capacity (MW)
- 300 Capacity is the interconnection request in CAISO Public Queue Report. The 1 generator listed in EIA-860M Preliminary Monthly Electric Generator Inventory (listed under Sources) total 449 MW nameplate.
- Connects at
- Kramer Substation 230kVConnection point750 MW active (4 of 17 projects).
- EIA plant
- 64852
At this site
2 records at Daggett 3At this siteGrouped by the same grid connection point and project name. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Daggett 3 this record | Solar + storage | 300 | Built |
| Another phase high confidence | DAGGETT SOLAR 2 | Solar + storage | 182 | Built |
Also at this interconnection point (15)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- Aratina Solar Center 2 Solar + storage, 200 MW, under construction at Kramer Substation 230kV
- ARATINA SOLAR CENTER 1 Solar + storage, 200 MW, contracted at Kramer Substation 230kV
- WESTON STORAGE Storage, 200 MW, studied at Kramer Substation 230kV
- Overnight Solar Solar + storage, 150 MW, under construction at Kramer Substation 230kV
- LOCKHART SOLAR 2 Solar + storage, 150 MW, built at Kramer Substation 230kV
- SAND SOLAR Solar, 300 MW, withdrawn at Kramer Substation 230kV
- FREMONT VALLEY PRESERVATION Solar, 245 MW, withdrawn at Kramer Substation 230kV
- COSO SOLAR 2 Solar, 206.5 MW, withdrawn at Kramer Substation 230kV
- GHOST TOWN SOLAR Solar, 203.9 MW, withdrawn at Kramer Substation 230kV
- KRAMER SOLAR Solar, 200 MW, withdrawn at Kramer Substation 230kV
- GRAVEL HILLS WIND & SOLAR Wind, 150 MW, withdrawn at Kramer Substation 230kV
- HARPER LAKE ENERGY STORAGE Storage, 140 MW, withdrawn at Kramer Substation 230kV
- SEGS10 SOLAR Solar, 81.2 MW, withdrawn at Kramer Substation 230kV
- COSO SOLAR 1 Solar, 78.2 MW, withdrawn at Kramer Substation 230kV
- COSO #1 Geothermal, 15 MW, withdrawn at Kramer Substation 230kV
Timeline
- Observed as built in EIA-860M (source status: “Operating (EIA-860M operating generator inventory)”).
- Stated In-service date stated by CAISO.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.