Gum Swamp Solar, LLC: the source's site coordinate and 5 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Gum Swamp Solar, LLC
Solar
Key facts
Solar Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- Duke Energy Progress East (CPLE)
- In-service date
- (stated)
- Location
- Scotland County, North Carolina
Details
Who’s behind it
- Developer
- Headwater Energy, LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Solar source: “Solar Photovoltaic”
- EIA plant
- 70302 generator 22
Timeline
- Stated In-service date stated by EIA-860M.
- Observed as under construction in EIA-860M (source status: “(U) Under construction, less than or equal to 50 percent complete”).
- EIA-860M Preliminary Monthly Electric Generator Inventory: Proposed cod 2027-05-01 → 2027-03-01.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources EIA-860M
Around this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Longhorn Holdings Postponed | Solar | 7.3 mi | 5 |
| AMAZON DATA SERVICES, INC. - ENERGY WAY TECH CAMPUS Built | Large load | 7.8 mi | |
| Scotch Grove Solar Filed | Solar | 8.7 mi | 80 |
| Friesian Holdings Postponed | Solar | 11.1 mi | 75 |
| Collard Holdings Solar Postponed | Solar | 12.3 mi | 10 |
Sources EIA-860M · EPA ICIS-Air