US energy projects and power plants, from first filing to retirement.
Public records, free to use. Every record links to its source.
- Bruce nuclear power plant—6,944MW
- Grand Coulee32%6,809MW
- Vogtle91%4,658MW
- West County Energy Center49%4,263MW
- Palo Verde84%4,209.6MW
- W A Parish39%4,008.4MW
- Browns Ferry92%3,854MW
- Darlington nuclear power plant—3,736MW
- Bowen43%3,498.6MW
- Crystal River52%3,449MW
- Barry46%3,343.5MW
- Gibson36%3,339.5MW
- Pickering nuclear power plant—3,244MW
- Turkey Point76%2,978.4MW
- Manatee28%2,951.2MW
- John E Amos35%2,932.6MW
- Peach Bottom87%2,876.4MW
- Bath County—2,862MW
- Jack McDonough75%2,848.4MW
- James H Miller Jr77%2,822MW
- South Texas Project85%2,708.6MW
- Fort Myers40%2,680.9MW
- Scherer33%2,673MW
- Oconee94%2,666.7MW
- Gavin Power, LLC53%2,600MW
- Trimble County36%2,594.1MW
- SunZia Wind South—2,561.2MW
- Roxboro33%2,558.2MW
- Watts Bar Nuclear Plant89%2,539.8MW
- TalenEnergy Susquehanna89%2,532MW
- Belews Creek45%2,491.2MW
- Chief Joseph55%2,456.2MW
- Cross38%2,451.5MW
- Braidwood Generation Station91%2,449.8MW
- Byron Generating Station92%2,449.8MW
- Martin39%2,448.5MW
- Sequoyah84%2,441MW
- McGuire89%2,440.6MW
- Comanche Peak94%2,430MW
- Robert Moses Niagara67%2,429.1MW
- Union Power Station60%2,428MW
- Catawba87%2,410.2MW
- Labadie73%2,389.4MW
- PSEG Salem Generating Station92%2,381.8MW
- Martin Lake41%2,379.6MW
- Sanford45%2,377.8MW
- LaSalle Generating Station90%2,340MW
- Jim Bridger36%2,326MW
- Diablo Canyon91%2,323MW
- H L Culbreath Bayside Power Station39%2,293.7MW
| Bruce nuclear power plant | Plant | Operating | 6,944MW | — | 1977 | GEM | |||
| Grand Coulee | Plant | Operating | 6,809MW | 32% | 1941 | EIA-860M | |||
| Vogtle | Plant | Operating | 4,658MW | 91% | 1987 | EIA-860M | |||
| West County Energy Center | Plant | Operating | 4,263MW | 49% | 2009 | EIA-860M | |||
| Palo Verde | Plant | Operating | 4,209.6MW | 84% | 1986 | EIA-860M | |||
| W A Parish | Plant | Operating | 4,008.4MW | 39% | 1958 | EIA-860M | |||
| Browns Ferry | Plant | Operating | 3,854MW | 92% | 1974 | EIA-860M | |||
| Darlington nuclear power plant | Plant | Operating | 3,736MW | — | 1990 | GEM | |||
| Bowen | Plant | Operating | 3,498.6MW | 43% | 1971 | EIA-860M | |||
| Crystal River | Plant | Operating | 3,449MW | 52% | 1982 | EIA-860M | |||
| Barry | Plant | Operating | 3,343.5MW | 46% | 1954 | EIA-860M | |||
| Gibson | Plant | Operating | 3,339.5MW | 36% | 1975 | EIA-860M | |||
| Pickering nuclear power plant | Plant | Operating | 3,244MW | — | 1971 | GEM | |||
| Turkey Point | Plant | Operating | 2,978.4MW | 76% | 1972 | EIA-860M | |||
| Manatee | Plant | Operating | 2,951.2MW | 28% | 1976 | EIA-860M | |||
| John E Amos | Plant | Operating | 2,932.6MW | 35% | 1971 | EIA-860M | |||
| Peach Bottom | Plant | Operating | 2,876.4MW | 87% | 1974 | EIA-860M | |||
| Bath County | Plant | Operating | 2,862MW | — | 1985 | EIA-860M | |||
| Jack McDonough | Plant | Operating | 2,848.4MW | 75% | 1971 | EIA-860M | |||
| James H Miller Jr | Plant | Operating | 2,822MW | 77% | 1978 | EIA-860M | |||
| South Texas Project | Plant | Operating | 2,708.6MW | 85% | 1988 | EIA-860M | |||
| Fort Myers | Plant | Operating | 2,680.9MW | 40% | 1958 | EIA-860M | |||
| Scherer | Plant | Operating | 2,673MW | 33% | 1982 | EIA-860M | |||
| Oconee | Plant | Operating | 2,666.7MW | 94% | 1973 | EIA-860M | |||
| Gavin Power, LLC | Plant | Operating | 2,600MW | 53% | 1974 | EIA-860M | |||
| Trimble County | Plant | Operating | 2,594.1MW | 36% | 1990 | EIA-860M | |||
| SunZia Wind South | Plant | Operating | 2,561.2MW | — | 2026 | EIA-860M | |||
| Roxboro | Plant | Operating | 2,558.2MW | 33% | 1966 | EIA-860M | |||
| Watts Bar Nuclear Plant | Plant | Operating | 2,539.8MW | 89% | 1996 | EIA-860M | |||
| TalenEnergy Susquehanna | Plant | Operating | 2,532MW | 89% | 1983 | EIA-860M | |||
| Belews Creek | Plant | Operating | 2,491.2MW | 45% | 1974 | EIA-860M | |||
| Chief Joseph | Plant | Operating | 2,456.2MW | 55% | 1955 | EIA-860M | |||
| Cross | Plant | Operating | 2,451.5MW | 38% | 1984 | EIA-860M | |||
| Braidwood Generation Station | Plant | Operating | 2,449.8MW | 91% | 1988 | EIA-860M | |||
| Byron Generating Station | Plant | Operating | 2,449.8MW | 92% | 1985 | EIA-860M | |||
| Martin | Plant | Operating | 2,448.5MW | 39% | 1994 | EIA-860M | |||
| Sequoyah | Plant | Operating | 2,441MW | 84% | 1981 | EIA-860M | |||
| McGuire | Plant | Operating | 2,440.6MW | 89% | 1981 | EIA-860M | |||
| Comanche Peak | Plant | Operating | 2,430MW | 94% | 1990 | EIA-860M | |||
| Robert Moses Niagara | Plant | Operating | 2,429.1MW | 67% | 1961 | EIA-860M | |||
| Union Power Station | Plant | Operating | 2,428MW | 60% | 2003 | EIA-860M | |||
| Catawba | Plant | Operating | 2,410.2MW | 87% | 1985 | EIA-860M | |||
| Labadie | Plant | Operating | 2,389.4MW | 73% | 1970 | EIA-860M | |||
| PSEG Salem Generating Station | Plant | Operating | 2,381.8MW | 92% | 1971 | EIA-860M | |||
| Martin Lake | Plant | Operating | 2,379.6MW | 41% | 1977 | EIA-860M | |||
| Sanford | Plant | Operating | 2,377.8MW | 45% | 1969 | EIA-860M | |||
| LaSalle Generating Station | Plant | Operating | 2,340MW | 90% | 1984 | EIA-860M | |||
| Jim Bridger | Plant | Operating | 2,326MW | 36% | 1974 | EIA-860M | |||
| Diablo Canyon | Plant | Operating | 2,323MW | 91% | 1985 | EIA-860M | |||
| H L Culbreath Bayside Power Station | Plant | Operating | 2,293.7MW | 39% | 1965 | EIA-860M |
Generation ·
Interested in this project?
What is counted
- Counts follow the map: move it or pick a state.
- Planned and Construction: every project a register still lists.
- Withdrawn and canceled: not counted; the Projects list shows them.
- Operating and Idling or retired: plants, from EIA-860M (US) and GEM’s GIPT.
- No stage chosen: all stages together, retired plants left out.
- Built projects are drawn among the plants, never counted twice.
- Not on this map: projects placed only by county or state, or with the site withheld by license.
- They are counted, not drawn, once the view holds that whole area.
- Data center MW is demand, never added to generation.
Generation
Net generation ÷ (MW × hours), last 12 months or latest full year (EIA-923). US plants only.
Under Color: Underused, the least-run plants for their technology are darkest.
Independent: no utility, co-op or public power owner or operator on record (EIA-860). Plants only.
Pipelines and power lines
Gas pipelines and power lines, with gas processing and storage, LNG terminals, ethanol and renewable gas plants.
Power prices at hubs
Monthly average power price: a point where a hub's location is published, else one chip per market.
Wholesale price (nodes)
Day-ahead average over 12 months, the median of the pricing nodes placed in each county.
Industrial price (county)
Average revenue per MWh, not a tariff quote. The median of the utilities serving each county.
Fiber by county
Availability by county, not routes.
Unshaded: not stated.
Fiber providers (county, approx.). Providers reporting fiber availability somewhere in the county. Not a route to a site, not carrier-neutral or long-haul fiber.
Download grid data
- Power lines 203,951 rows · 68 MB
- Substations 69,120 rows · 7 MB
GeoParquet · snapshot Oct 10, 2026
© OpenStreetMap contributors, ODbL. A database you derive from these files must stay under ODbL.
Convert to GeoJSON or Shapefile:ogr2ogr -f GeoJSON lines.geojson lines.parquetogr2ogr -f 'ESRI Shapefile' lines.shp lines.parquet
Transmission lines layer: LBNL download page, Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0.