Show on map
Bryan Peaking — Power plant · Oil · American Mun Power-Ohio, IncMark Center Solar Project — Solar · OH · 90 MW · 20.5 km away
  • Combustion
  • Wind & solar
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Bryan Peaking

Power plant · Oil

Key facts

Power plant · Oilran 1% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1999
Net generation, 2025
597 MWh
Grid
12 kV to City of Bryan - (OH) (PJM)
Location
Williams County, Ohio
Operated by
American Mun Power-Ohio, IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2004 to 2025
Fuel burned MMBtu by year, 2004 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
27 years since 1999
Unused energy
94 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
11,658 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
12.50
Transmission owner
City of Bryan - (OH)
Balancing authority code
PJM
Balancing authority name
PJM Interconnection, LLC
Fuel burned (MMBtu), 20256,960
Capacity factor, 20250.006
Heat rate (Btu/kWh), 202511,658.3
Net generation (MWh), 2025597
Balancing authority codePJM

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Mark Center Solar Project Under construction Solar 20.5 km 90

Sources EIA-860M

Sources

Attribution