Byxbee Park Sanitary Landfill — Power plant · Biomass · WPI Packaging & Maint Co Inc888 Ross Data Center — Filed · Large load · CA · 6.1 mi away7999 Gateway Solar — Under construction · Solar · CA · 4.6 MW · 6.1 mi awayGateway#1&2 (Newark CA) — Announced · Solar · CA · 1.1 MW · 6.5 mi awayWaste Management Tri-Cities LFGTE — Postponed · Biomass · CA · 4.8 MW · 7.7 mi awaySV8 DATA CENTER — Large load · CA · 9.7 mi awayFremont CA AutoFactory — Under construction · Solar · CA · 3.8 MW · 9.7 mi awayEDGECORE DATA CENTER MECP1 SANTA CLARA 1 PROJECT — Large load · CA · 9.7 mi awayEdgecore -3580 — Filed · Large load · CA · 9.7 mi awayVANTAGE DATA CENTERS MANAGEMENT CO , LLC — Large load · CA · 9.8 mi awayPRIME DATA CENTERS — Built · Large load · CA · 10.5 mi awayKifer BESS 1 — Under construction · Storage · CA · 50 MW · 10.6 mi awaySJC02 & SJC03 DATA CENTER — Large load · CA · 10.7 mi away1200 Memorex Skybox Data Center — Filed · Large load · CA · 10.8 mi away4054 Digital Realty — Built · Large load · CA · 10.9 mi awaySKYBOX DATA CENTER — Built · Large load · CA · 11.2 mi awayLBA Data Center West — Filed · Large load · CA · 11.3 mi awayHAYWARD DATA CENTER — Large load · CA · 11.6 mi awayDC-N (San Jose data centre) — Filed · Large load · CA · 14.5 mi away
  • Wind & solar
  • Storage
  • Bioenergy
  • Loads
  • In development
  • Under construction
  • Operating
  • Retired
  • Stage not stated
  • Size not stated
  • 10 · 100 · 1,000 MW

Byxbee Park Sanitary Landfill

Power plant · Biomass

Key facts

Power plant · Biomassran 5% of 2004 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1990
Net generation, 2004
883 MWh
Location
Santa Clara County, California
Operated by
WPI Packaging & Maint Co IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2004
Fuel burned MMBtu by year, 2001 to 2004
  • Gas
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Landfill Gas”
Age
36 years since 1990

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2004
Capacity retired
2 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Landfill Gas1 MWRetiredDecember 2004
GEN2Landfill Gas1 MWRetiredDecember 2004

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Transmission lines within 15 mi (10)
Connection points within 15 mi (1)
  • KEN-OKJ 60 kV CAISO · 60 kV · 1 request nearby, nearest 10.6 mi
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units GEN1, GEN2 scheduled to retire, 2 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · LBNL · CAISO · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
888 Ross Data Center Filed Large load 6.1 mi
7999 Gateway Solar Under construction Solar 6.1 mi 4.6
Gateway#1&2 (Newark CA) Announced Solar 6.5 mi 1.1
Waste Management Tri-Cities LFGTE Postponed Biomass 7.7 mi 4.8
SV8 DATA CENTER Unknown Large load 9.7 mi
Fremont CA AutoFactory Under construction Solar 9.7 mi 3.8
EDGECORE DATA CENTER MECP1 SANTA CLARA 1 PROJECT Unknown Large load 9.7 mi
Edgecore -3580 Filed Large load 9.7 mi
VANTAGE DATA CENTERS MANAGEMENT CO , LLC Unknown Large load 9.8 mi
PRIME DATA CENTERS Built Large load 10.5 mi
Kifer BESS 1 Under construction Storage 10.6 mi 50
SJC02 & SJC03 DATA CENTER Unknown Large load 10.7 mi
1200 Memorex Skybox Data Center Filed Large load 10.8 mi
4054 Digital Realty Built Large load 10.9 mi
SKYBOX DATA CENTER Built Large load 11.2 mi
LBA Data Center West Filed Large load 11.3 mi
HAYWARD DATA CENTER Unknown Large load 11.6 mi
DC-N (San Jose data centre) Filed Large load 14.5 mi

Sources FAA OE/AAA · EIA-860M · EPA ICIS-NPDES · EPA ICIS-Air · CAISO

Sources

  • FAA OE/AAAOpen license · retrieved Nov 16, 2026
  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EPA ICIS-NPDESOpen license · retrieved Nov 16, 2026
  • EPA ICIS-AirOpen license · retrieved Nov 16, 2026
  • CAISOOpen license, with credit · retrieved Nov 18, 2026Source: California ISO

Attribution