Duane Arnold Energy Center — Power plant · Nuclear · NextEra Energy Duane Arnold LLCData Center — Filed · Large load · IA · 13.0 mi awayMobile Cranes (Cedar Rapids data centre) — Filed · Large load · IA · 13.3 mi awayQTS Data Center — Filed · Large load · IA · 13.3 mi awayCedar Rapids Data Center — Filed · Large load · IA · 13.6 mi awayQTS East Data Center - Temporary Crane — Filed · Large load · IA · 13.6 mi awaySuffolk/DataCenter/MobileCrane/DC5/Laydown — Filed · Large load · IA · 14.1 mi away
  • Clean firm
  • Loads
  • In development
  • Retired
  • Size not stated
  • 10 · 100 · 1,000 MW

Duane Arnold Energy Center

Power plant · Nuclear

Key facts

Power plant · Nuclearran 88% of 2019 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1975
Net generation, 2019
5,235,716 MWh
Location
Linn County, Iowa
Operated by
NextEra Energy Duane Arnold LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2020
Fuel burned MMBtu by year, 2001 to 2020
  • Nuclear

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Nuclear source: “Nuclear”
Age
51 years since 1975
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100000500399
Location id
L100000500178
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
November 2020
Capacity retired
679.5 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Nuclear679.5 MWRetiredNovember 2020

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
MISO
Transmission lines within 15 mi (5)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 1 scheduled to retire, 679.5 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Data Center Filed Large load 13.0 mi
Mobile Cranes (Cedar Rapids data centre) Filed Large load 13.3 mi
QTS Data Center Filed Large load 13.3 mi
Cedar Rapids Data Center Filed Large load 13.6 mi
QTS East Data Center - Temporary Crane Filed Large load 13.6 mi
Suffolk/DataCenter/MobileCrane/DC5/Laydown Filed Large load 14.1 mi

Sources FAA OE/AAA

Sources

  • FAA OE/AAAOpen license · retrieved Nov 16, 2026

Attribution