Show on map
Gas Utilization Facility — Power plant · Biomass · City of San Diego - (CA)CA National City Terminal Ave — Solar · CA · 1.1 MW · 12.3 km awayEnerSmart Imperial Beach BESS — Storage · CA · 6 MW · 17.6 km awayEnerSmart Mesa Heights Sub Station — Storage · CA · 3 MW · 18.4 km awayL3 Harris San Diego — Solar · CA · 1.6 MW · 19.1 km awayAlvarado Hydro Facility — Hydro · CA · 1.4 MW · 22.3 km awayEnerSmart Murray BESS — Storage · CA · 21 MW · 24.3 km away
  • Wind & solar
  • Storage
  • Bioenergy
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Gas Utilization Facility

Power plant · Biomass

Key facts

Power plant · Biomassran 57% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1985
Net generation, 2025
30,461 MWh
Grid
15 kV to San Diego Gas & Electric Co (CISO)
Location
San Diego County, California
Operated by
City of San Diego - (CA)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Other Waste Biomass”
Age
41 years since 1985
Heat rate
10,878 Btu/kWh 2025
All 7 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
15
Transmission owner
San Diego Gas & Electric Co
Balancing authority code
CISO
Balancing authority name
California Independent System Operator
Eia status
By code
OP
Mw
4.60
Units
2
OS
Mw
1.50
Units
1
Standby mw
0
Status rule
some_units_idle
In service mw
6.10
Out of service mw
1.50
Fuel burned (MMBtu), 2025331,361
Capacity factor, 20250.570
Heat rate (Btu/kWh), 202510,878.2
Net generation (MWh), 202530,461
Balancing authority codeCISO

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
CA National City Terminal Ave Under construction Solar 12.3 km 1.1
EnerSmart Imperial Beach BESS Postponed Storage 17.6 km 6
EnerSmart Mesa Heights Sub Station Under construction Storage 18.4 km 3
L3 Harris San Diego Under construction Solar 19.1 km 1.6
Alvarado Hydro Facility Postponed Hydro 22.3 km 1.4
EnerSmart Murray BESS Postponed Storage 24.3 km 21

Sources EIA-860M

Sources

Attribution