H Allen Franklin Combined Cycle
Power plant · Gas, combined cycle
Key facts
Power plant · Gas, combined cycleran 69% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2002
- Net generation, 2025
- 12,061,177 MWh
- Grid
- 230 kV to Georgia Power Co (SOCO)
- Location
- Lee County, Alabama
- Operated by
- Southern Power Co
Output
- Gas
Details
Who’s behind it
- Owner
- Southern CO
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
- Age
- 24 years since 2002
- Unused energy
- 5,421 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 7,006 Btu/kWh 2025
All 8 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 84,506,250 |
| Capacity factor, 2025 | 0.690 |
| Heat rate (Btu/kWh), 2025 | 7,006.5 |
| Net generation (MWh), 2025 | 12,061,177 |
| Balancing authority code | SOCO |
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Southern Power Co | Operator | EIA-860M | ||
| SOUTHERN CO | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
Timeline
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| H Allen Franklin Combined Cycle Postponed | Gas, combined cycle | 0.0 mi | 688.1 |
| ADDITIONS AND MODIFICATIONS TO SYNOVUS DATA CENTER Unknown | Large load | 10.6 mi |
Sources EIA-860M · EPA ICIS-NPDES