Heat Recovery Coke Facility — Power plant · Other · Cokenergy IncW 167th St — Under construction · Solar · IL · 1.5 MW · 12.5 mi awayDATA CENTER — Built · Large load · IN · 13.8 mi awayHOBART DATA CENTER MASS GRADING - 1 — Under construction · Large load · IN · 13.9 mi awayRobbins Community Power LLC — Postponed · Biomass · IL · 55 MW · 14.7 mi away
  • Wind & solar
  • Unspecified fuel
  • Loads
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Heat Recovery Coke Facility

Power plant · Other

Key facts

Power plant · Otherran 51% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1998
Net generation, 2025
419,318 MWh
Grid
138 kV to Northern Indiana Pub Serv Co (MISO)
Location
Lake County, Indiana
Operated by
Cokenergy Inc

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Gas
  • Unspecified fuel

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Other source: “All Other”
Age
28 years since 1998
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
138
Transmission owner
Northern Indiana Pub Serv Co
Balancing authority code
MISO
Balancing authority name
Midcontinent Independent Transmission System Operator, Inc..
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110066942526
Subparts reported
C, Q
NAICS code
324199
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1007287
Fuel burned (MMBtu), 20251,430,712
Capacity factor, 20250.506
Net generation (MWh), 2025419,318
Balancing authority codeMISO

Ownership

4 companies4
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Cokenergy Inc Operator EIA-860M
SUNCOKE ENERGY INC Owner 85.0% Dec 31, 2023 EPA GHGRP
DTE ENERGY CO Owner 15.0% Dec 31, 2023 EPA GHGRP
Primary Energy Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
W 167th St Under construction Solar 12.5 mi 1.5
DATA CENTER Built Large load 13.8 mi
HOBART DATA CENTER MASS GRADING - 1 Under construction Large load 13.9 mi
Robbins Community Power LLC Postponed Biomass 14.7 mi 55

Sources EIA-860M · EPA ICIS-NPDES

Sources

Attribution