Hell Gate
Power plant · Gas, combustion turbine
Key facts
Power plant · Gas, combustion turbineran 15% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2001
- Net generation, 2025
- 119,912 MWh
- Grid
- 138 kV to Consolidated Edison Co-NY Inc (NYIS)
- Location
- Bronx County, New York
- Operated by
- New YORK Power AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
Details
Who’s behind it
- Owner
- New YORK Power AuthoritySource100.0%, EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT), as of 31 Dec 2023
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Age
- 25 years since 2001
- Unused energy
- 704 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 10,622 Btu/kWh 2025
All 8 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 1,273,729 |
| Capacity factor, 2025 | 0.146 |
| Heat rate (Btu/kWh), 2025 | 10,622.2 |
| Net generation (MWh), 2025 | 119,912 |
| Balancing authority code | NYIS |
Timeline
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Astoria Gas Turbines Postponed | Gas, combustion turbine | 1.4 km | 431 |
| New York University Central Plant Under construction | Gas, combined cycle | 1.5 km | 5.5 |
| Wintergreen C Clean Energy LLC Under construction | Storage | 2.2 km | 4.9 |
| Wintergreen B Clean Energy LLC Under construction | Storage | 2.2 km | 4.9 |
| Wintergreen D Clean Energy LLC Under construction | Storage | 2.2 km | 4.9 |
| Wintergreen Clean Energy, LLC Under construction | Storage | 2.2 km | 4.9 |
| Lincoln Medical and Mental Health Center Under construction | Oil | 2.4 km | 1 |
| Warbler Clean Energy LLC Under construction | Storage | 4.5 km | 2.3 |
| Piping Plover Clean Energy, LLC Under construction | Storage | 4.5 km | 2.3 |
| Ravenswood Postponed | Storage | 5.4 km | 316 |
| Lobelia Clean Energy LLC Under construction | Storage | 6.2 km | 4.9 |
| Lobelia 4452 Clean Energy LLC Under construction | Storage | 6.2 km | 4.9 |
| Roseate Tern Clean Energy LLC Under construction | Storage | 9.5 km | 3.3 |
| CYXTERA - NJ2X Built | Large load | 10.7 km | |
| NISA Electric Generation Project × 2 units Permitted | Storage | 11.5 km | 392.5 |
| Eastern BlueBird Clean Energy LLC Under construction | Storage | 11.7 km | 4.4 |
| Northern Cardinal Clean Energy, LLC Under construction | Storage | 11.7 km | 4.4 |
| CDIL DATA CENTRE USA LLC Built | Large load | 12.3 km | |
| EQUINIX Built | Large load | 13.5 km | |
| CORESITE NY4 DATA CENTER Under construction | Large load | 13.6 km | |
| EQUINIX LLC Built | Large load | 13.8 km | |
| Blue Aster B Clean Energy LLC Under construction | Storage | 13.9 km | 4.9 |
| Blue Aster Clean Energy LLC Under construction | Storage | 13.9 km | 4.9 |
| Blue Aster C Clean Energy LLC Under construction | Storage | 13.9 km | 4.9 |
| Water Willow A Clean Energy LLC Under construction | Storage | 14.8 km | 3.9 |
| Water Willow B Clean Energy LLC Under construction | Storage | 14.8 km | 3.9 |
| Linden Clean Energy, LLC Under construction | Storage | 15.3 km | 3.7 |
| Coral Honeysuckle Clean Energy LLC Under construction | Storage | 15.3 km | 3.7 |
| NJ TRANSITGRID Postponed | Gas, combustion turbine | 16.3 km | 136.1 |
| Gowanus Gas Turbines Generating Postponed | Gas, combustion turbine | 17.1 km | 93 |
| Jamaica Community Energy, LLC Under construction | Storage | 18.0 km | 4.9 |
| Bensonhurst Energy Storage 1 LLC Under construction | Storage | 18.2 km | 5 |
| CLIFTON DATA CENTER Built | Large load | 19.7 km | |
| Heron Clean Energy, LLC Under construction | Storage | 20.2 km | 4.9 |
| Kennedy International Airport Cogen Postponed | Gas, combustion turbine | 20.7 km | 50 |
| RAR DEVELOPMENT ASSOCIATES × 2 units Built | Large load | 21.1 km | |
| Bayonne Energy Center Under construction | Storage | 22.4 km | 49.8 |