Show on map
- Combustion
- Wind & solar
- Storage
- Loads
- In development
- Under construction
- Operating
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Combustion
- Wind & solar
- Storage
- Loads
- In development
- Under construction
- Operating
- Size not stated
Kaiser Downey: location and 15 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Kaiser Downey
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 95% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2012
- Net generation, 2025
- 8,360 MWh
- Grid
- 0.5 kV to Southern California Edison Co (CISO)
- Location
- Los Angeles County, California
- Operated by
- Bloom Energy 2009 PPASourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
- Biomass and waste
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, other source: “Other Natural Gas”
- Age
- 14 years since 2012
- Heat rate
- 7,000 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 58,521 |
| Capacity factor, 2025 | 0.954 |
| Heat rate (Btu/kWh), 2025 | 7,000.1 |
| Net generation (MWh), 2025 | 8,360 |
| Balancing authority code | CISO |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Bandini - SLLAX710 Under construction | Solar | 7.2 km | 1.3 |
| South Bay Dis Ctr 6-SLLAX680 Under construction | Solar | 12.2 km | 1.3 |
| Fordyce - SLLAX680 Under construction | Solar | 12.2 km | 1.3 |
| South Bay Dis Ctr 12 - SLLAX104 Under construction | Solar | 12.3 km | 1.2 |
| Dominguez - SLLAX512 Under construction | Solar | 12.7 km | 1.3 |
| PRIME DATA CENTER VERNON Built | Large load | 13.1 km | |
| CPA 3777 Workman Postponed | Solar | 13.9 km | 1.9 |
| Watson Cogeneration Withdrawn | Gas, combined cycle | 15.7 km | 94.2 |
| LATTC South Campus Solar Postponed | Solar | 18.2 km | 1.1 |
| Torrance Dis Ctr 2 - SLLAX100 Under construction | Solar | 19.2 km | 1.4 |
| Elevate Pier S Filed | Storage | 19.3 km | 70 |
| Marici Under construction | Storage | 19.5 km | 400 |
| Westminster Reliability Project, LLC Under construction | Storage | 19.5 km | 110 |
| Glenarm BESS Plant Filed | Storage | 23.2 km | 25 |
| California Institute of Technology Postponed | Gas, combined cycle | 24.4 km | 16.5 |
Sources EIA-860M · EPA ICIS-NPDES · CAISO