Show on map
Mandalay — Power plant · Gas, steam turbine · GenOn California South, LPMission Rock Energy Center Hybrid — Postponed · Gas, combustion turbine · CA · 300 MW · 17.5 km awaySanta Paula Energy Storage — Postponed · Storage · CA · 5 MW · 23.8 km away
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbineran 3% of 2017 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1959
Net generation, 2017
151,953 MWh
Location
Ventura County, California

Output

Net generation MWh by year, 2001 to 2018
Fuel burned MMBtu by year, 2001 to 2018
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
67 years since 1959
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110000517717
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1001448
Balancing authority codeCISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
February 2018
Capacity retired
574 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
03Natural Gas Fired Combustion Turbine138 MWRetiredFebruary 2018
1Natural Gas Steam Turbine218 MWRetiredFebruary 2018
2Natural Gas Steam Turbine218 MWRetiredFebruary 2018
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Natural Gas Steam Turbine436 MW
Natural Gas Fired Combustion Turbine138 MW

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
CISO
Transmission lines within 25 km (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
GenOn California South, LP Operator EIA-860M
NRG Energy, Inc Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Units 03, 1, 2 scheduled to retire, 574 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Mission Rock Energy Center Hybrid Postponed Gas, combustion turbine 17.5 km 300
Santa Paula Energy Storage Postponed Storage 23.8 km 5

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution