Show on map
Raeford - Richmond 230 kV — Transmission lineScotch Grove Solar — Filed · Solar · NC · 80 MW · 0.0 mi awayInnovative Solar 53 — Postponed · Solar · NC · 40 MW · 0.1 mi awayWestfield Solar, LLC — Under construction · Solar · NC · 40 MW · 0.1 mi awayGum Swamp Solar, LLC — Under construction · Solar · NC · 80 MW · 1.1 mi awayAMAZON DATA SERVICES, INC. - ENERGY WAY TECH CAMPUS — Built · Large load · NC · 1.1 mi awayCollard Holdings Solar — Postponed · Solar · NC · 10 MW · 6.8 mi awayLonghorn Holdings — Postponed · Solar · NC · 5 MW · 8.2 mi awayFriesian Holdings — Postponed · Solar · NC · 75 MW · 8.3 mi awayIsland Grove Solar — Postponed · Solar · NC · 2 MW · 10.9 mi awayHowardtown Farm — Postponed · Solar · NC · 10 MW · 14.8 mi away
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Raeford - Richmond 230 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
230 kV
States crossed
US-NC
Owner (as stated)
Duke Energy Progress

Details

Who’s behind it

Owner
Duke Energy Progress

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
40
Substations at the ends (as the source names them)
Raeford to Richmond
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itduke energy progress
HIFLD line ID109426
Voltage class220-287 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Scotch Grove Solar Filed Solar 0.0 mi 80
Innovative Solar 53 Postponed Solar 0.1 mi 40
Westfield Solar, LLC Under construction Solar 0.1 mi 40
Gum Swamp Solar, LLC Under construction Solar 1.1 mi 80
AMAZON DATA SERVICES, INC. - ENERGY WAY TECH CAMPUS Built Large load 1.1 mi
Collard Holdings Solar Postponed Solar 6.8 mi 10
Longhorn Holdings Postponed Solar 8.2 mi 5
Friesian Holdings Postponed Solar 8.3 mi 75
Island Grove Solar Postponed Solar 10.9 mi 2
Howardtown Farm Postponed Solar 14.8 mi 10

Sources EIA-860M · EPA ICIS-Air

Sources

Attribution