- Combustion
- Wind & solar
- Under construction
- Retired
- 10 · 100 · 1,000 MW
Map
- Combustion
- Wind & solar
- Under construction
- Retired
South Bay Fuel Cell Plant: location and 2 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
South Bay Fuel Cell Plant
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 51% of 2021 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2012
- Net generation, 2021
- 6,660 MWh
- Location
- San Diego County, California
- Operated by
- BioFuels Point Loma LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
- Biomass and waste
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
- Technology
- Gas, other source: “Other Natural Gas”
- Age
- 14 years since 2012
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | CISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- December 2021
- Capacity retired
- 1.5 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| SBFC | Other Natural Gas | 1.5 MW | Retired | December 2021 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- CISO
Transmission lines within 15 mi (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit SBFC scheduled to retire, 1.5 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| EnerSmart Imperial Beach BESS Postponed | Storage | 3.2 mi | 6 |
| CA National City Terminal Ave Under construction | Solar | 8.2 mi | 1.1 |
Sources EIA-860M