United Cogen — Power plant · Gas, combined cycle · United Cogen IncSan Francisco Intl Airport Ct Project — Postponed · Gas, combustion turbine · CA · 48 MW · 0.8 km awayAmeresco Ox Mountain — Filed · Biomass · CA · 3 MW · 14.7 km awaySan Francisco Electric Reliability Proj — Withdrawn · Gas, combustion turbine · CA · 151.5 MW · 17.1 km awaySan Leandro 10 - sleba702 — Under construction · Solar · CA · 1 MW · 20.6 km awayDynegy Oakland Power Plant — Announced · Storage · CA · 43.3 MW · 20.7 km awayHAYWARD DATA CENTER — Large load · CA · 24.5 km away
  • Combustion
  • Wind & solar
  • Storage
  • Bioenergy
  • Loads
  • In development
  • Under construction
  • Retired
  • Stage not stated
  • Size not stated
  • 10 · 100 · 1,000 MW

United Cogen

Power plant · Gas, combined cycle

Key facts

Power plant · Gas, combined cycleran 71% of 2011 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1985
Net generation, 2011
192,949 MWh
Location
San Mateo County, California
Operated by
United Cogen IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2012
Fuel burned MMBtu by year, 2001 to 2012
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
Age
41 years since 1985

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
January 2012
Capacity retired
31 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
G-1Natural Gas Fired Combined Cycle23 MWRetiredJanuary 2012
G-2Natural Gas Fired Combined Cycle8 MWRetiredJanuary 2012

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Transmission lines within 25 km (10)
Connection points within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units G-1, G-2 scheduled to retire, 31 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · LBNL · CAISO · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
San Francisco Intl Airport Ct Project Postponed Gas, combustion turbine 0.8 km 48
Ameresco Ox Mountain Filed Biomass 14.7 km 3
San Francisco Electric Reliability Proj Withdrawn Gas, combustion turbine 17.1 km 151.5
San Leandro 10 - sleba702 Under construction Solar 20.6 km 1
Dynegy Oakland Power Plant Announced Storage 20.7 km 43.3
HAYWARD DATA CENTER Unknown Large load 24.5 km

Sources EIA-860M · CAISO · EPA ICIS-NPDES

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • CAISOOpen license, with credit · retrieved Nov 11, 2026Source: California ISO
  • EPA ICIS-NPDESOpen license · retrieved Nov 8, 2026

Attribution