West River Road - Riverside 115 kV: route and 12 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
West River Road - Riverside 115 kV
Transmission line
- Mapped route length
- Mapped route length: sourceLBNL · Open license, with creditmiles
- Voltage
- 115 kV
- States crossed
- US-MN
- Owner (as stated)
- Northern States Power Minnesota
Details
Who’s behind it
- Owner
- Northern States Power Minnesota
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Mapped route length (miles)
- 2
- Substations at the ends (as the source names them)
- West River Road to Riverside
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
| Attribute | Value |
|---|---|
| Owner, as the source states it | northern states power minnesota |
| HIFLD line ID | 133433 |
| Voltage class | 100-161 kV |
Sources
1 sourceSources LBNL
Sources
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
Around this line
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| SUPERCOMPUTER LLC Built | Large load | 0.2 mi | |
| FAIRVIEW DATA CENTER Built | Large load | 2.4 mi | |
| TC Solar RCE Postponed | Solar | 5.2 mi | 1 |
| HB FULLER CO - DATA CENTER - ARDEN HILLS Built | Large load | 6.3 mi | |
| OPTUM TECHNOLOGY Built | Large load | 7.0 mi | |
| FIS GLOBAL Built | Large load | 8.2 mi | |
| DATA RECOGNITION CORP Built | Large load | 8.9 mi | |
| DATABANK MSP3 Built | Large load | 9.8 mi | |
| IRON GATE DATA CENTERS - EAGAN Built | Large load | 11.6 mi | |
| DATABANK - EAGAN - MSP2 Built | Large load | 12.4 mi | |
| Black Dog Postponed | Gas, combined cycle | 12.6 mi | 760 |
| EAGAN 5 MW DATA CENTER Built | Large load | 14.0 mi |
Sources EPA ICIS-Air · EIA-860M