Tap 138kV 39500 West Columbia Main - 110505 Sweeny Co-Gen LP Ckt 1

Open in Projects

Line tap

Key facts

Line tap
Voltage
138 kV
Capacity queued
201 MW, 1 active project
Queue
ERCOT
Kind
Line tap
Voltage
138 kV
Bus number
—
Jurisdiction
US-TX
Substation
—
Active queued (MW)
201 across 1 project
Withdrawn or canceled (MW)
0 across 0
Built (MW)
0 across 0
About this point

A grid connection point as ERCOT GIS Report (Generator Interconnection Status) names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Storage 201 1 1

Projects connecting here

All 1 in Projects

Sources

1 source

Sources ERCOT

Sources

  • ERCOTOpen license · retrieved Nov 4, 2026

Every source and license · Attribution