Substation
Key facts
Substation- Capacity queued
- 144 MW, 1 active project
Projects connecting here
| Status | Name | Company | Technology | Capacity (MW) | Jurisdiction | Proposed online |
|---|---|---|---|---|---|---|
| Filed | Beinneun 2 Windfarm | Beinneun 2 Limited | Wind | 144 | GB | 31 Oct 2037 |
Sources
1 sourceSources NESO
Supported by National Energy SO Open Data
Sources
- NESO Transmission Entry Capacity (TEC) RegisterSupported by National Energy SO Open Data