SHAWFAIR 400KV SUBSTATION

Open in Projects

Substation

Key facts

Substation
Voltage
400 kV
Capacity queued
240 MW, 1 active project
Queue
NESO
Kind
Substation
Voltage
400 kV
Bus number
—
Jurisdiction
GB
Substation
—
Active queued (MW)
240 across 1 project
Withdrawn or canceled (MW)
0 across 0
Built (MW)
0 across 0
About this point

A grid connection point as NESO Transmission Entry Capacity (TEC) Register names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Storage 240 1 1

Projects connecting here

All 1 in Projects

Sources

1 source

Sources NESO

Supported by National Energy SO Open Data

Sources

  • NESOOpen license, with credit · retrieved Nov 11, 2026Supported by National Energy SO Open Data

Every source and license · Attribution