Substation

Key facts

Substation
Voltage
500 kV
Capacity queued
800.1 MW, 2 active projects
Queue
CAISO
Kind
Substation
Voltage
500 kV
Bus number
—
Jurisdiction
US-CA
Substation
—
Active queued (MW)
800.1 across 2 projects
Withdrawn or canceled (MW)
1,050 across 2
Built (MW)
0 across 0
About this point

A grid connection point as CAISO Public Queue Report names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Storage 800.1 2 2
Solar 0 0 2

Projects connecting here

All 4 in Projects

Sources

1 source

Sources CAISO

Sources

  • CAISOOpen license, with credit · retrieved Nov 15, 2026Source: California ISO

Every source and license · Attribution