Substation

Key facts

Substation
Voltage
230 kV
Capacity queued
175 MW, 1 active project

Projects connecting here

Projects that connect at this point: active first, then built, other and withdrawn, each by capacity.
Status Name Technology Capacity (MW) Jurisdiction Proposed online
Contracted BLACK DIAMOND ES2 Storage 175 US-CA Jun 18, 2031
Withdrawn STEEL CITY ENERGY STORAGE Storage 650 US-CA Jun 30, 2025
Withdrawn PITTSBURG POWER PLANT - CCU Gas, combined cycle 611 US-CA Sep 30, 2012
Withdrawn COMMANDER ENERGY STORAGE Storage 500 US-CA Jul 19, 2032
Withdrawn STEEL CITY BATTERY STORAGE Storage 220 US-CA Mar 1, 2029
Withdrawn STONEMAN Storage 220 US-CA Nov 1, 2024
Withdrawn BLACK DIAMOND ENERGY STORAGE 2 Storage 200 US-CA May 1, 2021
Withdrawn MALLARD ENERGY STORAGE PROJECT Storage 81.1 US-CA Jun 1, 2021

Sources

1 source

Sources CAISO

Sources

  • CAISOOpen license, with credit · retrieved Nov 17, 2026Source: California ISO