500kV line to the new Midpoint switching station

Open in Projects

Line tap

Key facts

Line tap
Voltage
500 kV
Capacity queued
0 MW, 0 active projects
Queue
CAISO
Kind
Line tap
Voltage
500 kV
Bus number
—
Jurisdiction
US-CA
Substation
—
Active queued (MW)
0 across 0 projects
Withdrawn or canceled (MW)
640 across 1
Built (MW)
0 across 0
About this point

A grid connection point as CAISO Public Queue Report names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Gas, combined cycle 0 0 1

Projects connecting here

All 1 in Projects

Sources

1 source

Sources CAISO

Sources

  • CAISOOpen license, with credit · retrieved Nov 18, 2026Source: California ISO