Stockton A #1 line 60 kV, Cogeneration National 60 kV tap

Open in Projects

Unparsed

Key facts

Unparsed
Voltage
60 kV
Capacity queued
0 MW, 0 active projects
Queue
CAISO
Kind
Unparsed
Voltage
60 kV
Bus number
—
Jurisdiction
US-CA
Substation
—
Active queued (MW)
0 across 0 projects
Withdrawn or canceled (MW)
5 across 1
Built (MW)
0 across 0
About this point

A grid connection point as CAISO Public Queue Report names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Biomass 0 0 1

Projects connecting here

All 1 in Projects

Sources

1 source

Sources CAISO

Sources

  • CAISOOpen license, with credit · retrieved Nov 16, 2026Source: California ISO

Every source and license · Attribution