8619 Encinal - 8627 Lemay Box Bay 138kV line

Open in Projects

Line tap

Key facts

Line tap
Voltage
138 kV
Capacity queued
211.4 MW, 1 active project

Recent changes at this point

The newest recorded changes to the projects that connect here, most recent first.
Observed Change Project Source
Entered the queue here as studied Vazlon Solar SLF ERCOT GIS Report (Generator Interconnection Status)

Sources

1 source

Sources ERCOT

Sources

  • ERCOTOpen license · retrieved Nov 4, 2026

Every source and license · Attribution