Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek

Open in Projects

Line tap

Key facts

Line tap
Voltage
345 kV
Capacity queued
709.2 MW, 2 active projects

Recent changes at this point

The newest recorded changes to the projects that connect here, most recent first.
Observed Change Project Source
Entered the queue here as studied River Boat Storage ERCOT GIS Report (Generator Interconnection Status)
Entered the queue here as studied River Boat Solar ERCOT GIS Report (Generator Interconnection Status)