Show on map
Compass DatacenterMICROSOFT CORP - OLIVE AVE — Large load · AZ · 1.3 km awayMicrosoft Phx 83 (El Mirage data centre) — Large load · AZ · 2.0 km awayAligned Phx 7 — Large load · AZ · 4.8 km awayMERIT 2 — Large load · AZ · 5.9 km awayWhite Tank Energy Storage — Storage · AZ · 100 MW · 8.8 km awayQTS DC13 - Temp Crane - NE — Large load · AZ · 10.9 km awayQTS PHX3 Data Center — Large load · AZ · 11.7 km awayPHX 70 - MICROSOFT DATA CENTER — Large load · AZ · 13.6 km awayPHX73 (Goodyear data centre) — Large load · AZ · 13.9 km awayDesert Bloom — Storage · AZ · 150 MW · 14.1 km awayMICROSOFT CORP - CITRUS RD — Large load · AZ · 14.2 km awayVantage AZ15 — Large load · AZ · 14.8 km awayCOMPASS DATACENTERS PHX I — Large load · AZ · 15.4 km awayCOMPASS DATA CENTER - MOONRAKER — Large load · AZ · 15.7 km awayQTS DATA CENTER — Large load · AZ · 17.6 km awayCrane (Avondale data centre) — Large load · AZ · 17.9 km awayStream Data Center — Large load · AZ · 18.2 km awayPHX16 Data Center — Large load · AZ · 18.2 km awayPrime Data Center — Large load · AZ · 18.3 km awaySierra Luna Energy Storage — Storage · AZ · 150 MW · 18.8 km awayVantage Data Center 21 — Large load · AZ · 19.4 km awayPHX01 / PHX02 / PHX03 / PHX05 — Large load · AZ · 22.3 km awayAPS - ALIGNED ENERGY DATA CENTER — Large load · AZ · 22.3 km away
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Compass Datacenter

Data center

Kind
Data center
Location
Maricopa County, Arizona

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Kind
Data center source: “Data Center”
Capacity (MW)
Not stated
  • Selected as a data center because the facility name says data center. EPA ECHO ICIS-NPDES construction stormwater coverage (data-centre sites, national)
  • Selected as a data center because the facility name says data center. EPA ECHO ICIS-Air national facility download (data-centre selection, placed through FRS)

Timeline

  • Observed as under construction in EPA ICIS-NPDES (source status: “EFF”).

“Stated” dates are the source’s plan, not a commitment.

About these dates

Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.

Around this project

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
MICROSOFT CORP - OLIVE AVE Built Large load 1.3 km
Microsoft Phx 83 (El Mirage data centre) Filed Large load 2.0 km
Aligned Phx 7 Filed Large load 4.8 km
MERIT 2 Built Large load 5.9 km
White Tank Energy Storage Under construction Storage 8.8 km 100
QTS DC13 - Temp Crane - NE Filed Large load 10.9 km
QTS PHX3 Data Center Built Large load 11.7 km
PHX 70 - MICROSOFT DATA CENTER Built Large load 13.6 km
PHX73 (Goodyear data centre) Filed Large load 13.9 km
Desert Bloom Under construction Storage 14.1 km 150
MICROSOFT CORP - CITRUS RD Built Large load 14.2 km
Vantage AZ15 Under construction Large load 14.8 km
COMPASS DATACENTERS PHX I Built Large load 15.4 km
COMPASS DATA CENTER - MOONRAKER Built Large load 15.7 km
QTS DATA CENTER Under construction Large load 17.6 km
Crane (Avondale data centre) Filed Large load 17.9 km
Stream Data Center Built Large load 18.2 km
PHX16 Data Center Filed Large load 18.2 km
Prime Data Center Under construction Large load 18.3 km
Sierra Luna Energy Storage Announced Storage 18.8 km 150
Vantage Data Center 21 Under construction Large load 19.4 km
PHX01 / PHX02 / PHX03 / PHX05 Built Large load 22.3 km
APS - ALIGNED ENERGY DATA CENTER Built Large load 22.3 km