Projects in development
Supply side: grid queues, permits and planned plants · Suggest a missing project
Status not current MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0)
Status not current
The status is the one the file states on that date, not the register’s current one.
What this view shows
Showing 1,974 active projects (announced to under construction). Hidden: 0 withdrawn or cancelled.
7 projects no register lists any more are hidden. Show them
Save this search as an alert Free, daily or weekly.
| Status | Name. Sort by name, A to Z | Technology | Capacity (MW), sorted descending. Sort by capacity, smallest first | Location | Company | Proposed online. Sort by proposed online date, latest first | Source |
|---|---|---|---|---|---|---|---|
| Studied (source status: active) overdue by 4.9 years (target commercial-operation date 2021-12-24) | Q255 | Solar + storage | 2,000 MW | Coconino, AZ | — | Online 24 Dec 2021 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 5 months (target commercial-operation date 2026-06-01) | 489 | Gas, other | 1,689 MW | Roane, TN | — | Online 1 Jun 2026 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | Q92 | Solar + storage | 1,650 MW | San Bernardino, CA | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.1 years (target commercial-operation date 2025-10-03) | 483 | Gas, other | 1,600 MW | Stewart, TN | — | Online 3 Oct 2025 | us.lbnl.queued_up |
| Permitted (source status: Consents Approved) overdue by 9 months (target commercial-operation date 2026-01-31) | East Anglia Three | Offshore wind | 1,320 MW | East Anglia Project Three Offshore Platform, United Kingdom | East Anglia Three Limited | Online 31 Jan 2026 | NESO |
| Filed (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 1.5 years (target commercial-operation date 2025-05-13) | Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem | Gas, other | 1,231.7 MW | Iberville, LA | — | Online 13 May 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 4.4 years (target commercial-operation date 2022-06-01) | Q68 | Solar + storage | 1,200 MW | Los Angeles, CA | — | Online 1 Jun 2022 | us.lbnl.queued_up |
| Filed (source status: suspended) overdue by 1.6 years (target commercial-operation date 2025-04-14) | IC-942 | Solar + storage | 1,200 MW | Glynn, GA | — | Online 14 Apr 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.9 years (target commercial-operation date 2024-12-31) | G0678 | Solar | 1,200 MW | Morrow, OR | — | Online 31 Dec 2024 | us.lbnl.queued_up |
| Permitted (source status: Consents Approved) overdue by 1.6 years (target commercial-operation date 2025-04-01) | Dogger Bank Project C | Offshore wind | 1,200 MW | Lackenby 400kV Substation, United Kingdom | Doggerbank Offshore Wind Farm Project 3 Projco Limited | Online 1 Apr 2025 | NESO |
| Filed (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 5 months (target commercial-operation date 2026-05-31) | Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1 | Gas, other | 1,166 MW | Orange, TX | — | Online 31 May 2026 | us.lbnl.queued_up |
| Under construction (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 1.8 years (target commercial-operation date 2025-01-31) | J955 | Gas, other | 1,165 MW | Sangamon, IL | — | Online 31 Jan 2025 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 8.4 years (target commercial-operation date 2018-07-01) | 257 | Gas, other | 1,132 MW | Shelby, TN | — | Online 1 Jul 2018 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 8.4 years (target commercial-operation date 2018-07-01) | G0501 | Gas, other | 1,100 MW | Klamath, OR | — | Online 1 Jul 2018 | us.lbnl.queued_up |
| Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 24.6 years (target commercial-operation date 2002-03-20) | J1813 | Gas, other | 1,005 MW | Desoto, MS | — | Online 20 Mar 2002 | us.lbnl.queued_up |
| Filed (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | 125 | Solar + storage | 1,000 MW | Apache, AZ | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Contracted (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 2.6 years (target commercial-operation date 2024-03-31) | J1490 | Other | 1,000 MW | Randolph, MO | — | Online 31 Mar 2024 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | Intermountain Power Agency | Solar + storage | 1,000 MW | Millard, UT | Intermountain Power Agency | Online 31 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | Q474 | Solar + storage | 1,000 MW | Maricopa, AZ | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | Q468 | Storage | 1,000 MW | Maricopa, AZ | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2025-12-31) | Q466 | Solar + storage | 1,000 MW | Yuma, AZ | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Filed (source status: suspended) overdue by 2.4 years (target commercial-operation date 2024-06-01) | Q379 | Solar + storage | 1,000 MW | Maricopa, AZ | — | Online 1 Jun 2024 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 5.9 years (target commercial-operation date 2020-12-31) | Q275 | Solar + storage | 1,000 MW | Navajo, AZ | — | Online 31 Dec 2020 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.9 years (target commercial-operation date 2024-12-31) | Q274 | Solar | 1,000 MW | Coconino, AZ | — | Online 31 Dec 2024 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.9 years (target commercial-operation date 2024-12-31) | G0687 | Solar | 900 MW | Sherman, OR | — | Online 31 Dec 2024 | us.lbnl.queued_up |
| Filed (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 10 months (target commercial-operation date 2025-12-31) | Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff | Gas, other | 824 MW | St. Louis, MO | — | Online 31 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 2.1 years (target commercial-operation date 2024-10-01) | J2186 | Solar | 820.6 MW | Fulton, IL | — | Online 1 Oct 2024 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 4.9 years (target commercial-operation date 2021-12-31) | G0615 | Solar + storage | 800 MW | Sherman, OR | — | Online 31 Dec 2021 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.4 years (target commercial-operation date 2025-06-15) | 23-234 | Solar + storage | 800 MW | Jefferson, OR | — | Online 15 Jun 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.4 years (target commercial-operation date 2025-06-15) | 23-233 | Solar + storage | 800 MW | Jefferson, OR | — | Online 15 Jun 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 10 months (target commercial-operation date 2026-01-01) | Company 257 | Storage | 800 MW | Clark, NV | — | Online 1 Jan 2026 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 11 months (target commercial-operation date 2025-12-01) | 435 | Solar + storage | 800 MW | Rosebud, MT | — | Online 1 Dec 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 8 months (target commercial-operation date 2026-03-01) | GI-2022-164 | Solar + storage | 800 MW | Imperial, CA | — | Online 1 Mar 2026 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 16.1 years (target commercial-operation date 2010-10-01) | LGE-GIS-2009-004 | Gas, other | 785 MW | Trimble, KY | — | Online 1 Oct 2010 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 4.1 years (target commercial-operation date 2022-10-01) | 416 | Gas, other | 780 MW | Colbert, AL | — | Online 1 Oct 2022 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 4.1 years (target commercial-operation date 2022-10-01) | 417 | Gas, other | 780 MW | Muhlenberg, KY | — | Online 1 Oct 2022 | us.lbnl.queued_up |
| Filed (source status: active) overdue by 1.9 years (target commercial-operation date 2024-12-31) | 103 | Other | 768 MW | Apache, AZ | — | Online 31 Dec 2024 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 17.1 years (target commercial-operation date 2009-10-01) | GI-2003-3 | Coal | 750 MW | Pueblo, CO | — | Online 1 Oct 2009 | us.lbnl.queued_up |
| Filed (source status: active) overdue by 3.0 years (target commercial-operation date 2023-10-31) | C012 | Wind | 750 MW | Wheatland, MT | — | Online 31 Oct 2023 | us.lbnl.queued_up |
| Filed (source status: suspended) overdue by 3.0 years (target commercial-operation date 2023-10-31) | 391 | Wind | 750 MW | US | — | Online 31 Oct 2023 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 5.2 years (target commercial-operation date 2021-09-01) | 357 | Wind | 750 MW | Rosebud, MT | — | Online 1 Sep 2021 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 5.2 years (target commercial-operation date 2021-09-01) | 356 | Wind | 750 MW | Rosebud, MT | — | Online 1 Sep 2021 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 1.8 years (target commercial-operation date 2025-01-08) | Q402 | Solar + storage | 750 MW | Navajo, AZ | — | Online 8 Jan 2025 | us.lbnl.queued_up |
| Studied (source status: active) overdue by 3.4 years (target commercial-operation date 2023-06-30) | Q317 | Solar + storage | 750 MW | Coconino, AZ | — | Online 30 Jun 2023 | us.lbnl.queued_up |
| Contracted (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 1.1 years (target commercial-operation date 2025-09-20) | J1246 | Gas, other | 725.2 MW | Iberville Parish, LA | — | Online 20 Sep 2025 | us.lbnl.queued_up |
| Contracted (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 6.6 years (target commercial-operation date 2020-03-31) | J351 | Gas, other | 715 MW | St. Joseph, IN | — | Online 31 Mar 2020 | us.lbnl.queued_up |
| Filed (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 2.4 years (target commercial-operation date 2024-05-30) | Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2 | Solar | 710 MW | Sherburne, MN | — | Online 30 May 2024 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 2.2 years (target commercial-operation date 2024-09-01) | Company MI | Solar + storage | 700 MW | Churchill, NV | — | Online 1 Sep 2024 | us.lbnl.queued_up |
| Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) overdue by 11 months (target commercial-operation date 2025-12-01) | J2846 | Solar | 700 MW | Pulaski, IN | — | Online 1 Dec 2025 | us.lbnl.queued_up |
| Contracted (source status: active) overdue by 11.7 years (target commercial-operation date 2015-03-01) | LGE-GIS-2013-001 | Oil | 691 MW | Jefferson, KY | — | Online 1 Mar 2015 | us.lbnl.queued_up |
Sources Berkeley Lab · NESO
Supported by National Energy SO Open Data
Sources
- LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.
- NESO Transmission Entry Capacity (TEC) RegisterSupported by National Energy SO Open Data