Show on map
345 kV line (OSM way 172367692) — Transmission lineWensowitch Solar Park — Permitted · Solar · TX · 146.1 MW · 3.6 mi awayItsee Solar — Postponed · Solar · TX · 53.3 MW · 7.9 mi awayBrittlebush Solar and Battery Storage — Postponed · Solar + storage · TX · 800 MW · 8.4 mi awayMalala — Postponed · Battery storage · TX · 200 MW · 8.6 mi awayBluebonnet Prairie Wind — Under construction · Wind · TX · 180 MW · 9.3 mi awayQTS Data Centers 6 and 7 — Filed · Large load · TX · 9.8 mi awayStream Fir Data Center — Filed · Large load · TX · 10.1 mi awayForest Grove - Dodd — Postponed · Solar + storage · TX · 302 MW · 10.3 mi awayArmadillo Solar Center — Under construction · Solar · TX · 150.5 MW · 10.5 mi awayDatabank 13 — Filed · Large load · TX · 10.9 mi awayElm Flats Solar — Under construction · Solar + storage · TX · 375.8 MW · 11.1 mi awayDatabank Red Oak Campus - DFW 11 — Filed · Large load · TX · 11.7 mi awaySTACK DFW02A (Lancaster data centre) — Under construction · Large load · TX · 11.9 mi awayQTS - DFW 3 - DC1 — Filed · Large load · TX · 12.0 mi awayKaufman Solar — Under construction · Solar · TX · 200 MW · 12.8 mi awayDolomite Storage — Filed · Battery storage · TX · 125.7 MW · 13.6 mi awayLANCASTER DATA CENTER — Under construction · Large load · TX · 13.6 mi awayMEI Temporary Crane (Lancaster data centre) — Filed · Large load · TX · 13.6 mi awayTX Dallas 7750 Dynasty Drive — Under construction · Solar · TX · 2.3 MW · 14.7 mi away
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

345 kV line (OSM way 172367692)

Transmission line

Key facts

Transmission line Operating
Mapped route length
Mapped route length: sourceOpenStreetMap power network, US — transmission lines and cables (69 kV and up, or voltage not tagged) and substations, from Geofabrik's US state extracts · Open license, with creditmiles
Voltage
345 kV
States crossed
US-TX

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Mapped route length (miles)
40
All 18 attributes from OpenStreetMap power network, US — transmission lines and cables (69 kV and up, or voltage not tagged) and substations, from Geofabrik's US state extracts
Attributes
AttributeValue
Powerline
Cables6
Osm id172367692
RegionUS-TX
Circuits2
Osm typeway
Frequency60
UndergroundNo
Voltage raw345000
Voltages kv345
Circuits raw2
Scope regionsUS-TX
Voltage class345 kV
Extract regionsUS-TX
Voltage unknownNo
Coverage regionsUS-TX
Voltage assumed kvNo
Vertex count source204

Sources

1 source

Sources OpenStreetMap

© OpenStreetMap contributors

Sources

  • OpenStreetMapOpen license, with credit · retrieved Oct 10, 2026© OpenStreetMap contributors. Power lines, cables and substations filtered and reshaped by Inframation from the OpenStreetMap elements in Overture Maps' base/infrastructure theme; this derived database is available under the Open Database License 1.0 as GeoParquet files at https://tiles.inframation.io/grid/osm-power/ (latest.json names the current version's files; licence: https://www.openstreetmap.org/copyright)

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Wensowitch Solar Park Permitted Solar 3.6 mi 146.1
Itsee Solar Postponed Solar 7.9 mi 53.3
Brittlebush Solar and Battery Storage Postponed Solar + storage 8.4 mi 800
Malala Postponed Battery storage 8.6 mi 200
Bluebonnet Prairie Wind Under construction Wind 9.3 mi 180
QTS Data Centers 6 and 7 Filed Large load 9.8 mi
Stream Fir Data Center Filed Large load 10.1 mi
Forest Grove - Dodd Postponed Solar + storage 10.3 mi 302
Armadillo Solar Center Under construction Solar 10.5 mi 150.5
Databank 13 Filed Large load 10.9 mi
Elm Flats Solar Under construction Solar + storage 11.1 mi 375.8
Databank Red Oak Campus - DFW 11 Filed Large load 11.7 mi
STACK DFW02A (Lancaster data centre) Under construction Large load 11.9 mi
QTS - DFW 3 - DC1 Filed Large load 12.0 mi
Kaufman Solar Under construction Solar 12.8 mi 200
Dolomite Storage Filed Battery storage 13.6 mi 125.7
LANCASTER DATA CENTER Under construction Large load 13.6 mi
MEI Temporary Crane (Lancaster data centre) Filed Large load 13.6 mi
TX Dallas 7750 Dynasty Drive Under construction Solar 14.7 mi 2.3

Sources ERCOT · EIA-860M · FAA OE/AAA · EPA ICIS-NPDES

Sources

  • ERCOTOpen license · retrieved Nov 28, 2026
  • EIA-860MOpen license · retrieved Nov 4, 2026
  • FAA OE/AAAOpen license · retrieved Nov 23, 2026
  • EPA ICIS-NPDESOpen license · retrieved Nov 16, 2026

Attribution