Show on map
Delray — Power plant · Gas, combustion turbine · DTE Electric CompanyEast Windsor cogeneration centre 2 — Gas, combustion turbine · Canada · 100 MW · 8.9 km awayCity of Detroit Greenfield — Solar · MI · 7 MW · 14.0 km awayCity of Detroit Castle Solar — Solar · MI · 10 MW · 14.7 km awayTrenton Channel Energy Center — Storage · MI · 220 MW · 20.2 km away123NET — Large load · MI · 22.6 km away
  • Combustion
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 12% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2000
Net generation, 2025
145,140 MWh
Grid
120 kV to ITC Transmission (MISO)
Location
Wayne County, Michigan

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
26 years since 2000
Unused energy
1,101 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
12,122 Btu/kWh 2025
All 7 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
120
Transmission owner
ITC Transmission
Balancing authority code
MISO
Balancing authority name
Midcontinent Independent Transmission System Operator, Inc..
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110071161708
Subparts reported
D
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1000674
Fuel burned (MMBtu), 20251,759,393
Capacity factor, 20250.117
Heat rate (Btu/kWh), 202512,122
Net generation (MWh), 2025145,140
Balancing authority codeMISO

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
DTE Electric Company Operator EIA-860M
DTE ENERGY CO Owner 100.0% 31 Dec 2023 EPA GHGRP

Timeline

  • In service · EIA-860M

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
East Windsor cogeneration centre 2 Under construction Gas, combustion turbine 8.9 km 100
City of Detroit Greenfield Permitted Solar 14.0 km 7
City of Detroit Castle Solar Under construction Solar 14.7 km 10
Trenton Channel Energy Center Under construction Storage 20.2 km 220
123NET Built Large load 22.6 km

Sources GEM · EIA-860M · Berkeley Lab · EPA ICIS-Air

Sources

Attribution