Drews Generating Facility: location and 27 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Drews Generating Facility
Power plant · Gas, combustion turbine
Key facts
Power plant · Gas, combustion turbineran 0% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2001
- Net generation, 2025
- 570 MWh
- Grid
- 66 kV to City of Colton - (CA) (CISO)
- Location
- San Bernardino County, California
- Operated by
- Colton Power LPSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Age
- 25 years since 2001
- Unused energy
- 392 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 15,170 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 8,647 |
| Capacity factor, 2025 | 0.002 |
| Heat rate (Btu/kWh), 2025 | 15,170.2 |
| Net generation (MWh), 2025 | 570 |
| Balancing authority code | CISO |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| CA Bloomington 2551 S Lilac Avenue Micro Under construction | Solar + storage | 2.4 km | 3 |
| Solar Photovoltaic Project #24 Postponed | Solar | 3.1 km | 4 |
| CA Riverside 2356 Fleetwood Dr. Under construction | Solar + storage | 6.0 km | 4 |
| Solar Photovoltaic Project #30 Postponed | Solar | 6.7 km | 1.5 |
| Solar Photovoltaic Project #28 Postponed | Solar | 8.2 km | 0.5 |
| Solar Photovoltaic Project #25 Postponed | Solar | 10.0 km | 4.5 |
| Solar Photovoltaic Project #27 Postponed | Solar | 10.0 km | 1 |
| SunE Redlands Postponed | Solar | 10.2 km | 1.5 |
| OES Biogas Power Under construction | Biomass | 12.5 km | 2.6 |
| Solar Photovoltaic Project #17 Postponed | Solar | 13.9 km | 0.5 |
| Redlands DC 9 - sline609 Under construction | Solar + storage | 14.0 km | 5 |
| Solar Photovoltaic Project #20 Postponed | Solar | 14.2 km | 3.5 |
| Solar Photovoltaic Project #14 Postponed | Solar | 14.2 km | 1.5 |
| Solar Photovoltaic Project #10 Postponed | Solar | 15.2 km | 0.5 |
| Solar Photovoltaic Project #18 Postponed | Solar | 15.2 km | 0.5 |
| Solar Photovoltaic Project #19 Postponed | Solar | 15.4 km | 5 |
| Solar Photovoltaic Project #04 Postponed | Solar | 15.4 km | 1.5 |
| Solar Photovoltaic Project #23 Postponed | Solar | 15.6 km | 0.5 |
| Energy Center Announced | Gas, combustion turbine | 17.4 km | 0.9 |
| Solar Photovoltaic Project #21 Postponed | Solar | 18.5 km | 2.5 |
| Solar Photovoltaic Project #12 Postponed | Solar | 19.3 km | 0.5 |
| Solar Photovoltaic Project #08 Postponed | Solar | 19.6 km | 0.5 |
| Solar Photovoltaic Project #31 Postponed | Solar | 19.8 km | 1 |
| Solar Photovoltaic Project #09 Postponed | Solar | 20.2 km | 0.5 |
| Roadhouse Energy Center Contracted | Storage | 20.8 km | 300 |
| Amazon - Moreno Valley Postponed | Solar | 23.5 km | 2.2 |
| RCWMD Badlands Landfill Gas Project Postponed | Biomass | 23.9 km | 1.2 |
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory