San Diego Community College — Power plant · Gas, other · Bloom EnergyEnerSmart Mesa Heights Sub Station — Under construction · Storage · CA · 3 MW · 1.6 mi awayL3 Harris San Diego — Under construction · Solar · CA · 1.6 MW · 2.2 mi awayAlvarado Hydro Facility — Postponed · Hydro · CA · 1.4 MW · 7.5 mi awayEnerSmart Murray BESS — Postponed · Storage · CA · 21 MW · 8.5 mi awayRancho Penasquitos — Under construction · Hydro · CA · 4.3 MW · 9.6 mi awayCA National City Terminal Ave — Under construction · Solar · CA · 1.1 MW · 10.9 mi awayPomerado Energy Storage, LLC — Postponed · Storage · CA · 6 MW · 11.9 mi awayEnerSmart El Cajon BESS — Postponed · Storage · CA · 3 MW · 14.1 mi away
  • Combustion
  • Clean firm
  • Wind & solar
  • Storage
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

San Diego Community College

Power plant · Gas, other

Key facts

Power plant · Gas, otherran 80% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2020
Net generation, 2025
7,010 MWh
Grid
0.5 kV to San Diego Gas & Electric Co (CISO)
Location
San Diego County, California
Operated by
Bloom EnergySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2022 to 2025
Fuel burned MMBtu by year, 2022 to 2025
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, other source: “Other Natural Gas”
Age
6 years since 2020
Heat rate
6,775 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
0.500
Transmission owner
San Diego Gas & Electric Co
Balancing authority code
CISO
Balancing authority name
California Independent System Operator
Fuel burned (MMBtu), 202547,495
Capacity factor, 20250.800
Heat rate (Btu/kWh), 20256,775.3
Net generation (MWh), 20257,010
Balancing authority codeCISO

Timeline

  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
EnerSmart Mesa Heights Sub Station Under construction Storage 1.6 mi 3
L3 Harris San Diego Under construction Solar 2.2 mi 1.6
Alvarado Hydro Facility Postponed Hydro 7.5 mi 1.4
EnerSmart Murray BESS Postponed Storage 8.5 mi 21
Rancho Penasquitos Under construction Hydro 9.6 mi 4.3
CA National City Terminal Ave Under construction Solar 10.9 mi 1.1
Pomerado Energy Storage, LLC Postponed Storage 11.9 mi 6
EnerSmart El Cajon BESS Postponed Storage 14.1 mi 3

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution