Werner: location and 21 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Werner
Power plant · Oil
Key facts
Power plant · Oilran 0% of 2014 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1972
- Net generation, 2014
- 1,175 MWh
- Location
- Middlesex County, New Jersey
- Operated by
- GenOn REMA, LLC
Output
- Oil
Details
Who’s behind it
- Owner
- NRG Energy, Inc
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Oil source: “Petroleum Liquids”
- Age
- 54 years since 1972
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Balancing authority code | PJM |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- May 2015
- Capacity retired
- 212 MW
- Generators retired
- 4
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GT1 | Petroleum Liquids | 53 MW | Retired | May 2015 |
| GT2 | Petroleum Liquids | 53 MW | Retired | May 2015 |
| GT3 | Petroleum Liquids | 53 MW | Retired | May 2015 |
| GT4 | Petroleum Liquids | 53 MW | Retired | May 2015 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- PJM
Transmission lines within 25 km (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| GenOn REMA, LLC | Operator | EIA-860M | ||
| NRG Energy, Inc | Owner | 100.0% | 31 Dec 2023 | EPA GHGRP |
Timeline
- Stated Units GT1, GT2, GT3, GT4 scheduled to retire, 212 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Gateway Energy Center, LLC Postponed | Gas, combined cycle | 7.6 km | 440 |
| Middlesex Energy Center LLC Postponed | Gas, combined cycle | 8.1 km | 570 |
| Elevate Arthur Kill Under construction | Storage | 13.0 km | 15.1 |
| Milltown Onsite BESS Under construction | Storage | 13.7 km | 13.2 |
| Swiftsure Postponed | Storage | 14.3 km | 121 |
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 16.6 km | |
| EVOQUE DATA CENTER SOLUTIONS - PNJ1 Built | Large load | 16.7 km | |
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 16.9 km | |
| NJ 1 DATA CENTER Built | Large load | 18.8 km | |
| Prologis - SLCNJ001 - Community Solar Under construction | Solar | 20.0 km | 3.2 |
| Coreweave Under construction | Large load | 20.4 km | |
| Staten Island Energy Storage 1 LLC Postponed | Storage | 20.8 km | 5 |
| Prologis - SLNNJ036 - Community Solar Under construction | Solar | 21.4 km | 1.6 |
| BPL NJ - Union Distribution Center Under construction | Solar | 21.6 km | 1.5 |
| Elizabeth Metropolitan Logistics Center Under construction | Solar | 22.3 km | 1.2 |
| FIDESSA Built | Large load | 22.4 km | |
| BPL NJ - Belmont Under construction | Solar | 22.7 km | 1.8 |
| MORGAN STANLEY DATA CENTER Built | Large load | 22.8 km | |
| BLOOMBERG DATA CENTER Built | Large load | 23.8 km | |
| Bayonne Energy Center Under construction | Storage | 24.1 km | 49.8 |
| AB Newark Solar Postponed | Solar | 24.2 km | 5.6 |
Sources EIA-860M · EPA ICIS-Air · EPA ICIS-NPDES · FAA OE/AAA
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA ECHO ICIS-Air national facility download (data-centre selection, placed through FRS)
- EPA ECHO ICIS-NPDES construction stormwater coverage (data-centre sites, national)
- FAA OE/AAA Part 77 obstruction evaluation case archives (data-centre sites, buildings and cranes)