Westwing — Power plant · Storage · AES Clean EnergyDesert Bloom — Storage · AZ · 150 MW · 1.1 km awayCompass Datacenter — Large load · AZ · 15.2 km awayMICROSOFT CORP - OLIVE AVE — Large load · AZ · 16.4 km awayMicrosoft Phx 83 (El Mirage data centre) — Large load · AZ · 17.1 km awayAligned Phx 7 — Large load · AZ · 17.5 km awayMERIT 2 — Large load · AZ · 17.8 km awayAPS - ALIGNED ENERGY DATA CENTER — Large load · AZ · 20.6 km awayPHX01 / PHX02 / PHX03 / PHX05 — Large load · AZ · 20.8 km awayQTS DC13 - Temp Crane - NE — Large load · AZ · 23.4 km awayWhite Tank Energy Storage — Storage · AZ · 100 MW · 23.9 km awayQTS PHX3 Data Center — Large load · AZ · 24.4 km away
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Storage

Key facts

Power plant · Storage Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2024
Net generation, 2025
-21,745 MWh
Grid
230 kV to Arizona Public Service Co (AZPS)
Location
Maricopa County, Arizona
Operated by
AES Clean EnergySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2024 to 2026

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Storage source: “Batteries”
Age
2 years since 2024
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
230
Transmission owner
Arizona Public Service Co
Balancing authority code
AZPS
Balancing authority name
Arizona Public Service Company
Fuel burned (MMBtu), 20250
Net generation (MWh), 2025-21,745
Balancing authority codeAZPS
Data notes (1)
  • Capacity factor, 2025 not shown: net generation -21745.0 MWh is not positive (the plant consumed at least as much as it produced over the year)

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Desert Bloom Under construction Storage 1.1 km 150
Compass Datacenter Under construction Large load 15.2 km
MICROSOFT CORP - OLIVE AVE Built Large load 16.4 km
Microsoft Phx 83 (El Mirage data centre) Filed Large load 17.1 km
Aligned Phx 7 Filed Large load 17.5 km
MERIT 2 Built Large load 17.8 km
APS - ALIGNED ENERGY DATA CENTER Built Large load 20.6 km
PHX01 / PHX02 / PHX03 / PHX05 Built Large load 20.8 km
QTS DC13 - Temp Crane - NE Filed Large load 23.4 km
White Tank Energy Storage Under construction Storage 23.9 km 100
QTS PHX3 Data Center Built Large load 24.4 km