Key facts

Substation
Voltage
500 kV
Capacity queued
1,150 MW, 1 active project
Queue
CAISO
Kind
Substation
Voltage
500 kV
Bus number
—
Jurisdiction
US-CA
Substation
—
Active queued (MW)
1,150 across 1 project
Withdrawn or canceled (MW)
550 across 1
Built (MW)
0 across 0
About this point

A grid connection point as CAISO Public Queue Report names it. Projects connect here; they are not necessarily built here. Totals count only the projects listed under Projects.

By technology

Projects at this point by technology, largest active capacity first.
Technology Active MW Active projects All projects
Solar + storage 1,150 1 2