AVEP BESS: location and 15 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
AVEP BESS
Power plant · Storage
Key facts
Power plant · Storage Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2025
- Grid
- 115 kV to Southern California Edison Co (CISO)
- Location
- Kern County, California
- Operated by
- Leeward Asset Management, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Storage source: “Batteries”
- Age
- 1 year since 2025
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 0 |
| Net generation (MWh), 2025 | -17,220 |
| Balancing authority code | CISO |
Data notes (1)
- Capacity factor, 2025 not shown: net generation -17220.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Rosamond South II Under construction | Storage | 8.2 km | 140 |
| Syracuse and Tours Renewable Energy Permitted | Solar + storage | 8.9 km | 80 |
| Camino Solar Hybrid Postponed | Storage | 10.5 km | 11 |
| Solar Star 3 Under construction | Solar + storage | 10.7 km | 24 |
| Solar Star 4 Under construction | Solar + storage | 10.7 km | 24 |
| Windhub Solar B, LLC Under construction | Solar | 16.6 km | 26.4 |
| Alpine Solar Withdrawn | Solar | 17.5 km | 66 |
| Willow Rock Energy Storage Center Contracted | Storage | 17.7 km | 500 |
| Gaskell West Storage 1, LLC Under construction | Storage | 18.9 km | 21.6 |
| Antelope Solar Farm Postponed | Solar | 19.2 km | 20 |
| Portal Ridge Solar A, LLC Postponed | Solar | 19.8 km | 19 |
| Tehachapi Wind Resource I Postponed | Wind | 20.7 km | 0.6 |
| Tehachapi Spindle Withdrawn | Storage | 23.3 km | 20 |
| Neenach Solar Center Postponed | Solar | 24.3 km | 1.5 |
| Sanborn Hybrid 3 Under construction | Solar + storage | 25.0 km | 1,400 |
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- CAISO Public Queue ReportSource: California ISO