Show on map
Olive — Power plant · Gas, steam turbine · City of Burbank Water and Power - (CA)Foothill Solar Project — Solar · CA · 1.1 MW · 11.2 km awayScholl Canyon — Biomass · CA · 12 MW · 11.4 km awayAB Van Nuys — Solar · CA · 1.6 MW · 15.7 km awayGlenarm BESS Plant — Storage · CA · 25 MW · 16.3 km awayLATTC South Campus Solar — Solar · CA · 1.1 MW · 16.5 km awayCalifornia Institute of Technology — Gas, combined cycle · CA · 16.5 MW · 17.9 km awayVan Norman Bypass Solar Project — Solar · CA · 2 MW · 19.9 km awayPRIME DATA CENTER VERNON — Large load · CA · 21.0 km away
  • Combustion
  • Wind & solar
  • Storage
  • Bioenergy
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbine Standby
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1959
Net generation, 2025
0 MWh
Grid
69 kV to City of Burbank Water and Power (LDWP)
Location
Los Angeles County, California

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
67 years since 1959
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Parents
Name
City of Burbank Water and Power
Share pct
100
Gem entity id
E100000002203
Unit ids
G100000402562, G100000402563
Location id
L100000401781
Eia plant ids
6013
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110055879250
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1001003
Eia status
By code
SB
Mw
109.7
Units
2
Standby mw
109.7
Status rule
majority_mw_standby
In service mw
109.7
Out of service mw
0
Fuel burned (MMBtu), 20250
Net generation (MWh), 20250
Balancing authority codeLDWP
Data notes (1)
  • Capacity factor, 2025 not shown: net generation 0.0 MWh is not positive (the plant consumed at least as much as it produced over the year)

Retirement

Capacity retired
62.2 MW
Generators retired
2
Capacity still in service
109.7 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
O3Natural Gas Fired Combustion Turbine24.4 MWRetiredDecember 2003
O4Natural Gas Fired Combustion Turbine37.8 MWRetiredDecember 2003

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
City of Burbank Water and Power
Balancing authority
Los Angeles Department of Water and Power
NERC region
WECC
Transmission lines within 25 km (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
City of Burbank Water and Power - (CA) Operator EIA-860M
Burbank Water and Power Owner 100.0% 31 Dec 2023 EPA GHGRP

Timeline

  • Stated Units O3, O4 scheduled to retire, 62.2 MW · EIA-860M
  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Foothill Solar Project Postponed Solar 11.2 km 1.1
Scholl Canyon Under construction Biomass 11.4 km 12
AB Van Nuys Announced Solar 15.7 km 1.6
Glenarm BESS Plant Filed Storage 16.3 km 25
LATTC South Campus Solar Postponed Solar 16.5 km 1.1
California Institute of Technology Postponed Gas, combined cycle 17.9 km 16.5
Van Norman Bypass Solar Project Postponed Solar 19.9 km 2
PRIME DATA CENTER VERNON Built Large load 21.0 km