Strata Manager, LLC
Independent power producer
Key facts
Independent power producer · 538.9 MW- Capacity held
- 538.9MW
- Assets
- 162
- States
- CA, MO, NC
- Registered in
- United States
- Parent
- No parent recordedNo parent recordedLike 48,119 of 50,272 companies here. Why
Gross output of plants with a stake
3 of 3 plantsOutputGross: each plant's whole output, whatever the stake. Equity share: each plant's output times the stake.Covers 3 of 3 plants with a stake: US plants with an EIA monthly series.100% of the output is from 3 plants recorded as wholly owned.3 plants: operator, wholly owned per EIA-860.Not included: 159 plants it operates without a recorded stake.Ownership as recorded today; each plant's output is its whole series. A plant's group is its technology; Unspecified fuel is EIA's "All Other", hydrogen, CHP with no fuel stated and plants with no technology on record.
- Solar
- Storage
Yearly totals
| Year | Solar | Storage | Total (MWh) |
|---|---|---|---|
| 2025 | 16,440 | -1,343 | 15,097 |
| 2024 | 18,962 | -1,116 | 17,846 |
| 2023 | 18,354 | — | 18,354 |
| 2022 | 19,144 | — | 19,144 |
| 2021 | 19,581 | — | 19,581 |
| 2020 (part year) | 704 | — | 704 |
Sources EIA-860 · EIA-860M · EIA
Sources
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
Assets 162
Assets
162
first 100 listed
Capacity
539 MW
- Solar: 539 MW, 100 assets
Operates 162 power plants
1–100 of 162AssetsThe first rows the register lists, sorted among themselves.
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Sources 2
Registers
2
Reuse terms
- 1 Open license
- 1 Open license, with credit
Latest read
2026-10-30
From its recordsSourcesThe registers behind this company's assets, projects and RFPs; the company record itself is derived from them.
Sources
-
View at source →
EIA-860M ·
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
Summary only: the source’s license keeps the full record at the source.
-
View at source →
GEM ·
Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)
Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. · license
In-file notice, About sheet of Global_Integrated_Power_September_2026_V2.xlsb (the owner's download, read 2026-10-26 with pyxlsb 1.0.10; decisions log 2026-10-26): "Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. (See the CC license for attribution requirements if sharing or adapting the data set.)" and "Please note records with a “TZ ID” in the Other IDs (unit/phase) column were partially or fully sourced from the TransitionZero, Solar Asset Mapper, August 2025. Copyright © TransitionZero, Solar Asset Mapper, August 2025. Distributed under a Creative Commons Attribution-Non-Commercial 4.0 International License (CC BY-NC 4.0)." Before it was read: no licence prose on the dataset page (retrieved 2026-10-23), which gives only "The recommended citation is "Global Integrated Power Tracker, Global Energy Monitor, September 2026 release.""; GEM's download form records "Creative Commons Attribution 4.0 International (CC BY 4.0) — /creative-commons-license" (https://api.globalenergymonitor.org/static/gem-download-form.bundle.js, sha256 e5ecbeab…905e5b, retrieved 2026-10-23).
Summary only: the source’s license keeps the full record at the source.
Around this company
Nearby 201
within 25 kmProjects
201
within 25 km
Nearest
0.0 km
Lake Solar Center LLC
All 201NearbyShowing all 201 nearby projects. The 50 nearest fill 49 rows, as a project's generator units share a row.
| Status | Name. Sort by name, A to Z | Type | MW. Sort by capacity, largest first | Distance, sorted ascending. Sort by distance, farthest first | Nearest asset |
|---|---|---|---|---|---|
| Postponed | Lake Solar Center LLC | Solar | 5 MW | 0.0 km away | nearest: Wilson Farm 1 |
| Under construction | McCartney | Gas, combustion turbine | 146.7 MW | 0.5 km away | nearest: Springfield Solar 1 LLC |
| Postponed | Howardtown Farm | Solar | 10 MW | 0.6 km away | nearest: Railroad Farm 2 |
| Postponed | Hawk Solar | Solar | 5 MW | 0.6 km away | nearest: Franklin Solar 2 |
| Postponed | Tyler Solar | Solar | 5 MW | 0.6 km away | nearest: Meriwether Farm |
| Postponed | Chatham Park Solar Farm | Solar | 20 MW | 0.7 km away | nearest: Tinker (NC) |
| Postponed | Alexis Solar | Solar | 5 MW | 0.7 km away | nearest: Lenoir Farm |
| Postponed | Longhorn Holdings | Solar | 5 MW | 0.8 km away | nearest: Rock Farm |
| Postponed | Solar Photovoltaic Project #27 | Solar | 1 MW | 0.9 km away | nearest: Inland Empire Energy Storage |
| Postponed | Aulander Solar | Solar | 5 MW | 0.9 km away | nearest: Bradley PV1 |
| Postponed | Solar Photovoltaic Project #25 | Solar | 4.5 MW | 1.0 km away | nearest: Inland Empire Energy Storage |
| Postponed | Izia Solar | Solar | 5 MW | 1.1 km away | nearest: Southerland Farm Solar |
| Postponed | Christina Solar | Solar | 3 MW | 1.1 km away | nearest: Martin Creek Farm LLC |
| Postponed | Soy Solar | Solar | 5 MW | 1.2 km away | nearest: Stone Solar |
| Postponed | Higgins Solar | Solar | 5 MW | 1.4 km away | nearest: North Nash Farm, LLC |
| Filed | Clark Creek Solar Plant | Solar + storage | 54 MW | 1.4 km away | nearest: Haynes Farm |
| Built | NTT GLOBAL DATA CENTERS | Large load | — | 1.4 km away | nearest: Strata Roof 1 |
| Postponed | E Nash PV3 | Solar | 26 MW | 1.5 km away | nearest: Nash 64 Farm |
| Under construction | Elm City BESS | Storage | 20 MW | 1.5 km away | nearest: Langley PV1 |
| Built | MICROSOFT CORPORATION, CLT17 | Large load | — | 1.5 km away | nearest: Two Lines Farm |
| Postponed | Collard Holdings Solar | Solar | 10 MW | 1.7 km away | nearest: Laurinburg Farm |
| Under construction | Baxter Creek Solar × 2 units | Solar | 60 MW | 1.8 km away | nearest: Mocksville Farm |
| Postponed | Spring Valley Farm | Solar | 5 MW | 2.2 km away | nearest: Spring Valley Farm 2, LLC |
| Postponed | Wilfork Solar | Solar | 5 MW | 2.2 km away | nearest: Wedge |
| Postponed | Rhubarb One | Solar | 5 MW | 2.3 km away | nearest: McCallum Farm |
| Postponed | Duroc Holdings | Solar | 5 MW | 2.3 km away | nearest: Mocksville Farm |
| Postponed | McCaskey Solar Farm, LLC | Solar | 2.4 MW | 2.4 km away | nearest: Jakana Solar |
| Postponed | Brooke Solar | Solar | 4.5 MW | 2.5 km away | nearest: Southerland Farm Solar |
| Postponed | Bonnie Solar | Solar | 5 MW | 2.8 km away | nearest: North Nash Farm, LLC |
| Postponed | Calypso Farm | Solar | 5 MW | 2.8 km away | nearest: Belafonte |
| Built | APPLE INC. | Large load | — | 2.8 km away | nearest: Sigmon Catawba Farm |
| Postponed | Eisenhower Solar | Solar | 5 MW | 2.8 km away | nearest: North Nash Farm, LLC |
| Postponed | Lotus Solar | Solar | 4 MW | 2.8 km away | nearest: Manning PV 1 |
| Postponed | Willoughby PV1 | Solar | 20 MW | 2.8 km away | nearest: Erwin Farm |
| Postponed | Sampson County Disposal | Biomass | 3.2 MW | 2.8 km away | nearest: Sampson Solar |
| Postponed | Cleveland Cnty Generating Facility | Gas, combustion turbine | 736 MW | 2.9 km away | nearest: Roper Farm, LLC |
| Built | MICROSOFT CORPORATION, CLT10 | Large load | — | 3.0 km away | nearest: Sigmon Catawba Farm |
| Postponed | Adams Solar | Solar | 2 MW | 3.0 km away | nearest: Moore Solar Farm |
| Filed | Black Walnut Solar, LLC | Solar + storage | 112 MW | 3.3 km away | nearest: Trent River Farm |
| Postponed | North Siler Farm | Solar | 5 MW | 3.4 km away | nearest: West Siler |
| Postponed | Cabaniss Solar | Solar | 4.2 MW | 3.6 km away | nearest: Tides Lane Farm |
| Postponed | RJ Solar | Solar | 5 MW | 3.6 km away | nearest: Old Catawba PV 1 |
| Postponed | Louisburg Solar | Solar | 5 MW | 3.7 km away | nearest: Franklin Solar 2 |
| Postponed | Wommack Farm | Solar | 5 MW | 4.2 km away | nearest: Kinston Davis Farm |
| Postponed | Weldon Solar | Solar | 5 MW | 4.8 km away | nearest: American Legion PV 1 |
| Postponed | Jordan Solar | Solar | 5 MW | 4.8 km away | nearest: Southerland Farm Solar |
| Postponed | Bear Poplar Solar | Solar | 5 MW | 4.8 km away | nearest: Redmon Solar Farm LLC |
| Under construction | Maiden Creek Battery | Storage | 50 MW | 5.1 km away | nearest: Sigmon Catawba Farm |
| Under construction | CLT04 LYLE CREEK DATA CENTER | Large load | — | 5.4 km away | nearest: Arndt Farm |